residential Ready to Move Source: rera.mh

Crystal New Era RERA Details - P99000025247, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Crystal New Era under registration P99000025247 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000025247
  • Project Name NEW ERA
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Palghar
  • Village Dhansar
  • Original Completion 30 December 2024
  • Revised Completion 30 December 2026
  • Project Area (in Sq.mt.) 2,306.98
  • Total Buildings/Towers 2
  • Documents 10 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 23 March 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name CRYSTAL REALTY

Promoters, Co-promoters & Members

NameRoleAddress
IBRAHIM SAIFUDDIN KAPADIAPartnerPalghar, MAHARASHTRA
MUSSABIR AMIN DAYERPartnerPalghar, MAHARASHTRA
SALIM AHMED ALI SAYYEDPartnerPalghar, MAHARASHTRA
FAUZAN JAVED MULLAPartnerPalghar, MAHARASHTRA
FAKHRUDDIN SIKANDER RAZAPartnerPalghar, MAHARASHTRA
MUZFFAR KHALIL GHANSARPartnerPalghar, MAHARASHTRA
IMAD SHAHNAWAZ KARARIPartnerPalghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
NEW ERA NEW ERA BLDG NO 4 TYPE E 0 0 6 0 0 NA
NEW ERA NEW ERA BLDG NO 3 TYPE D 0 0 6 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 70
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 70 units · avg area 24.82 Sq.mt.
  • NEW ERA BLDG NO 4 TYPE E
  • NEW ERA BLDG NO 3 TYPE D
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 31.74 4 0
1BHK 23.74 4 0
1BHK 29.88 2 0
1BHK 29.09 4 0
1BHK 36.94 1 0
1BHK 28.8 1 0
1BHK 24.39 16 0
1BHK 24.82 8 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 80.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 80.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • NEW ERA BLDG NO 4 TYPE E
  • NEW ERA BLDG NO 3 TYPE D
NEW ERA BLDG NO 4 TYPE E · Overall Progress 65%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work95%
Sanitary Fittings within the flats / premises
In Progress
% Work80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work60%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 CC COPY PART I OPT.Pdf.Pdf
2 PLAN OPT.Pdf.Pdf
3 CRYSTAL PAN CARD.Pdf.Pdf
4 LEGAL SERACH TITLE REPORT OPT.Pdf.Pdf
5 FORM B DECLARATION Opt.Pdf.Pdf
6 Affidavit In Form B Revised.Pdf.Pdf
7 STAR CRYSTAL REALTY DHANSAR AFS.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Branch Address 0
Country/City