RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P99000047067
- Project Name Crystal Residency
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Palghar
- Taluka Vasai
- Village Vasai-Virar City (M Corp)
- Original Completion 31 December 2023
- Project Area (in Sq.mt.) 3,769.15
- Total Buildings/Towers 4
- Documents 29 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Survey Number 229/B (Old S No. 229, H No. 2(Pt) & 3) | |
Boundary Details |
|
| Boundaries East 5 mtr and 6 m w Existing Road | Boundaries West 20 m w D P Road and S N 222 |
| Boundaries South S No 219 and 220 | Boundaries North 40 M W D P Road |
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting 50% | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation 100% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply % not reported | Sewerage 100% |
| Storm Water Drains 100% | Landscaping Tree Planting 90% | Street Lighting 100% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | Bassein Catholic Co op Bank Ltd |
|---|---|
| IFSC | BACB0000017 |