Deep Classic Tower RERA Details - P99000012178, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Deep Classic Tower under registration P99000012178 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000012178
  • Project Name DEEP CLASSIC TOWER
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 30 June 2021
  • Revised Completion 30 December 2022
  • Project Area (in Sq.mt.) 687.98
  • Total Buildings/Towers 1
  • Documents 11 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 September 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2021 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2022 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SAI SANGAM DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
NATALIN PATRICK DCUHNAPartnerPalghar, MAHARASHTRA
NILIMA PRAKASH PEGATPartnerPalghar, MAHARASHTRA
MADHUKAR KESHAV PATILPartnerPalghar, MAHARASHTRA
PATRICK CAITAN DCUNHAPartnerPalghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
DEEP CLASSIC TOWER DEEP CLASSIC TOWER 0 0 56 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 142
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 142 units · avg area 23.20 Sq.mt.
  • DEEP CLASSIC TOWER
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
AW1BHK3 23.51 4 4
AW1BHK4 23.56 9 6
BW1BHK2 23.19 31 11
AW1BHK1 22.79 18 7
BW1BHK3 23.51 4 4
BW1BHK1 22.79 18 6
AW1BHK5 23.59 9 3
BW1BHK5 23.59 9 3
AW1BHK2 23.19 31 20
BW1BHK4 23.56 9 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 95.0%
Storm Water Drains 90.0% Landscaping & Tree Planting 80.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 70.0% Solid Waste Management And Disposal 80.0%
Water Conservation /Rain Water Harvesting 90.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • DEEP CLASSIC TOWER
DEEP CLASSIC TOWER · Overall Progress 90%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work98%
Sanitary Fittings within the flats / premises
In Progress
% Work97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work92%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 Sangam Layout 1 .Pdf.Pdf
2 Sangam Layout 2 .Pdf.Pdf
3 Sangam Blue Print.Pdf.Pdf
4 Sangam PAN.Pdf.Pdf
5 Sangam Notary.Pdf.Pdf
6 Sangam Title Report.Pdf.Pdf
7 Sangam Search Report.Pdf.Pdf
8 Model Form Of Agreemen1 Sangam.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
IFSC BACB0000009
Branch Address FRENY ARCADE SAMEL PADA SOPARA NALLASOPARA WEST
Country/City