HDIL Paradise City RERA Details - P99000012642, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for HDIL Paradise City under registration P99000012642 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000012642
  • Project Name HDIL PARADISE CITY SECTOR 6
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Palghar
  • Village Mahim
  • Original Completion 30 June 2019
  • Revised Completion 30 June 2019
  • Project Area (in Sq.mt.) 34,575.62
  • Total Buildings/Towers 16
  • Documents 42 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 06 September 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2019 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
HDIL INDUSTRIAL PARKBESIDES LAXMI MARBLES CHANDANSAR ROAD VILLAGE CHANDANSAR VIRAR EAST32449CompletedOthers256272017-04-302017-07-25NoNA
HDIL RESIDENCY PARKOPP YAZOO PARK NARANGI BYPASS ROAD VILLAGE DONGRE VIRAR WEST27149CompletedResidential / Group Housing711992011-08-012015-10-14NoNA
GALAXY APARTMENTS WING ABEBHANDARY ESTATE KURLA EAST MUMBAI 4000245974.45CompletedResidential / Group Housing33142011-12-312017-06-19NoNA
PREMIER RESIDENCESPREMIER AUTO KURLA WEST MUMBAI - 40007015504.68CompletedIndustrial1110872012-12-302017-03-09NoNA
PREMIER EXOTICA IIPREMIER AUTO KIROL ROAD KURLA WEST MUMBAI 4000702151.39CompletedIndustrial1832013-06-302017-06-19NoNA
HARMONYNEW LINK ROAD GOREGAON WEST MUMBAI 40010411549.2CompletedIndustrial12212013-06-302017-07-04NoNA

Promoters, Co-promoters & Members

NameRoleAddress
SARANG WADHAWANManaging DirectorMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HDIL PARADISE CITY SECTOR 6 BUILDING NO 1 0 16 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 2 0 6 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 5 0 6 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 6 0 15 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 7 0 0 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 8 0 9 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 9 0 15 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 10 0 6 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 11 0 0 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 12 0 15 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 13 0 15 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 14 0 15 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 15 0 0 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 16 0 0 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 3 0 6 6 0 0 NA
HDIL PARADISE CITY SECTOR 6 BUILDING NO 4 0 16 6 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 986
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
RESIDENTIAL 812 units · avg area 45.13 Sq.mt.
COMMERCIAL 118 units · avg area 15.84 Sq.mt.
RESIDNETIAL 56 units · avg area 46.29 Sq.mt.
  • BUILDING NO 1
  • BUILDING NO 2
  • BUILDING NO 5
  • BUILDING NO 6
  • BUILDING NO 7
  • BUILDING NO 8
  • BUILDING NO 9
  • BUILDING NO 10
  • BUILDING NO 11
  • BUILDING NO 12
  • BUILDING NO 13
  • BUILDING NO 14
  • BUILDING NO 15
  • BUILDING NO 16
  • BUILDING NO 3
  • BUILDING NO 4
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
RESIDENTIAL 56.63 48 29
RESIDENTIAL 64.76 8 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 25.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains 35.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING NO 1
  • BUILDING NO 2
  • BUILDING NO 5
  • BUILDING NO 6
  • BUILDING NO 7
  • BUILDING NO 8
  • BUILDING NO 9
  • BUILDING NO 10
  • BUILDING NO 11
  • BUILDING NO 12
  • BUILDING NO 13
  • BUILDING NO 14
  • BUILDING NO 15
  • BUILDING NO 16
  • BUILDING NO 3
  • BUILDING NO 4
BUILDING NO 1 · Overall Progress 42%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work2%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 03 LAYOUT 2011.Pdf.Pdf
2 04 LAYOUT 2017.Pdf.Pdf
3 05 TYPE 14 N.Pdf.Pdf
4 06 TYPE 14A N.Pdf.Pdf
5 07 TYPE 14A1 N.Pdf.Pdf
6 08 TYPE 14B N.Pdf.Pdf
7 09 TYPE 14B1 N.Pdf.Pdf
8 10 TYPE 14C N.Pdf.Pdf
9 11 TYPE 14C1 N.Pdf.Pdf
10 02 NA ORDER PALGHAR 20 1 2017.Pdf.Pdf
11 26 TYPE 20A 1.Pdf.Pdf
12 27 TYPE 20A 2.Pdf.Pdf
13 28 TYPE 20A N.Pdf.Pdf
14 01 NA ORDER PALGHAR 6 6 2011.Pdf.Pdf
15 22 TYPE 17C N.Pdf.Pdf
16 23 TYPE 19.Pdf.Pdf
17 24 TYPE 19 N.Pdf.Pdf
18 25 TYPE 20 N.Pdf.Pdf
19 12 TYPE 14D N.Pdf.Pdf
20 13 TYPE 14D1 N.Pdf.Pdf
21 14 TYPE 14E N.Pdf.Pdf
22 15 TYPE 14E1 N.Pdf.Pdf
23 16 TYPE 17.Pdf.Pdf
24 17 TYPE 17 N.Pdf.Pdf
25 18 TYPE 17A.Pdf.Pdf
26 19 TYPE 17A.Pdf.Pdf
27 20 TYPE 17B.Pdf.Pdf
28 21 TYPE 17C.Pdf.Pdf
29 PANCARD.Pdf.Pdf
30 Jayesh Sompura IBC Application.Pdf.Pdf
31 Order NCLT 20082019.Pdf.Pdf
32 Order 17022020 NCLT Exclusion Of 106 Days.Pdf.Pdf
33 HDIL Provisional List Of Resolution Applicants.Pdf.Pdf
34 TC Paradise City Part 1.Pdf.Pdf
35 TC Paradise City Part 2.Pdf.Pdf
36 3TC Paradise City Part 3.Pdf.Pdf
37 TC Paradise City Part 4.Pdf.Pdf
38 TC Paradise City Part 5.Pdf.Pdf
39 Form B Sector 6 28072017.Pdf.Pdf
40 AL AFS Paradise City Sector 6.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Branch Address Bhandup West, Mumbai - 400 078
Country/City