residential Ready to Move Source: rera.mh

Himali Ramchandra Residency RERA Details - P99000024898, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Himali Ramchandra Residency under registration P99000024898 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000024898
  • Project Name Ramchandra Residency Building No. 2
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Vasai
  • Village Kopri
  • Original Completion 31 July 2023
  • Revised Completion 31 July 2025
  • Project Area (in Sq.mt.) 5,350.0
  • Total Buildings/Towers 1
  • Documents 25 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 March 2020 Expected commencement of civil works and foundation on site.
Original Completion 31 July 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 July 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Himali Construction

Promoters, Co-promoters & Members

NameRoleAddress
Viraj Bharat MakwanaPartnerPalghar, MAHARASHTRA
NIHIR JITENDRA MAKWANAPartnerPalghar, MAHARASHTRA
ANKIT BHARAT MAKWANAPartnerPalghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Ramchandra Residency Building No. 2 Ramchandra Residency Bldg no 2 110 0 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 80
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 65 units · avg area 32.90 Sq.mt.
2 BHK 15 units · avg area 50.34 Sq.mt.
  • Ramchandra Residency Bldg no 2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 28.52 1 1
1BHK 32.9 1 0
2BHK 43.76 1 1
1BHK 30.56 1 0
1BHK 26.31 1 0
1BHK 33.3 7 4
2BHK 50.84 6 3
1BHK 30.63 1 0
1BHK 31.16 1 1
1BHK 30.71 1 0
1BHK 30.31 1 1
1BHK 32.92 14 2
2BHK 51.51 7 3
1BHK 33.41 7 6
1BHK 39.17 1 1
1BHK 33.19 7 5
1BHK 33.17 7 3
1BHK 32.86 7 5
2BHK 45.68 1 1
1BHK 33.73 7 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 80.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Ramchandra Residency Bldg no 2
Ramchandra Residency Bldg no 2 · Overall Progress 90%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work95%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 LAYOUT PLAN.Pdf.Pdf
2 Fifth And Seventh Approved PLAN.Pdf.Pdf
3 FLOOR PLAN GR, 1st To 4th And 6th.Pdf.Pdf
4 1ST FLOOR PLAN.Pdf.Pdf
5 2ND TO 7TH FLOOR PLAN.Pdf.Pdf
6 8TH FLOOR PLAN.Pdf.Pdf
7 CFC BLUEPRINT.Pdf.Pdf
8 Pan Card.Pdf.Pdf
9 RPM MCHI 990000 MV 337.Pdf.Pdf
10 PCC.Pdf.Pdf
11 List Of Flats Mortgaged For RERA.Pdf.Pdf
12 Architect Certificate For 6th Slab.Pdf.Pdf
13 Purak Kararnama 2 Upload.Pdf.Pdf
14 Search Report.Pdf.Pdf
15 Title Clearance Report.Pdf.Pdf
16 Title Search Report Till 2019.Pdf.Pdf
17 Form B.Pdf.Pdf
18 Form B NEW.Pdf.Pdf
19 Notary.Pdf.Pdf
20 RERA Ramchandra Residency Draft.Pdf.Pdf
21 Deviation.Pdf.Pdf
22 RERA Ramchandra Residency Draft LATEST.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
IFSC BACB0000054
Branch Address ground floor ,makwana complex,veer savarkar road virar east
Country/City