residential Ready to Move Source: rera.mh

JSB Nakshatra Greens RERA Details - P99000005051, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for JSB Nakshatra Greens under registration P99000005051 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000005051
  • Project Name Nakshatra Greens
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 30 June 2018
  • Revised Completion 30 June 2019
  • Project Area (in Sq.mt.) 6,315.0
  • Total Buildings/Towers 4
  • Documents 17 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2019 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name JSB Buildcon LLP

Promoters, Co-promoters & Members

NameRoleAddress
Anita Sunil SeksariaPartnerMumbai Suburban, MAHARASHTRA
Samarth Sunil SeksariaPartnerMumbai Suburban, MAHARASHTRA
Jitendrakumar RankaPartnerMumbai Suburban, MAHARASHTRA
Sunil SeksariaPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Nakshatra Greens 6A 10 21 16 0 0 NA
Nakshatra Greens 6B 8 15 16 0 0 NA
Nakshatra Greens 6C 12 19 16 0 0 NA
Nakshatra Greens 6E 10 21 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 416
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
Residential 416 units · avg area 22.87 Sq.mt.
  • 6A
  • 6B
  • 6C
  • 6E
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Residential 23.88 110 105
Residential 18.59 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • 6A
  • 6B
  • 6C
  • 6E
6A · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 Self Attested CC Nakshatra Greens.Pdf.Pdf
2 NG.Pdf.Pdf
3 PAN JSB Buildcon.Pdf.Pdf
4 Declaration 1.Pdf.Pdf
5 Declaration 2.Pdf.Pdf
6 Declaration 3.Pdf.Pdf
7 Declaration 4.Pdf.Pdf
8 Declaration 5.Pdf.Pdf
9 Greens Phase I Declaration Q6 (1).Pdf.Pdf
10 Greens Phase I Declaration Q7 (4).Pdf.Pdf
11 Notary JSB Buildcon LLp Bldg 6.Pdf.Pdf
12 TitleSearch 01.Pdf.Pdf
13 TitleSearch 02.Pdf.Pdf
14 Greens Phase I Draft Agreement.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UNION BANK OF INDIA
IFSC UBIN0531715
Branch Address S V Road Goregaon West
Country/City