RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P99000004743
- Project Name Mahavir Heights
- Project Type Others
- Project Status Ready to Move
- State Maharashtra
- District Palghar
- Taluka Vasai
- Village Vasai-Virar City (M Corp)
- Original Completion 31 December 2019
- Revised Completion 30 June 2025
- Project Area (in Sq.mt.) 7,807.86
- Total Buildings/Towers 1
- Documents 3 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Survey Number 66/4 66/5 66/21 66/22/1/2/3/4 66/23 66/24/1/2 72/2/3 | |
Boundary Details |
|
| Boundaries East Bldg No 7 Wing B | Boundaries West 12 m Wide D P Road |
| Boundaries South Bldg No 7 Wing E | Boundaries North Bldg No 8 |
RERA Coordinates |
|
| Latitude, Longitude 19.470444000000001, 72.799972999999994 | |
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths 100.0% | Water Supply 100.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% |
| Storm Water Drains 100.0% | Landscaping & Tree Planting 100.0% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water % not reported | Solid Waste Management And Disposal % not reported |
| Water Conservation /Rain Water Harvesting 100.0% | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements 100.0% |
| Electrical Meter Room, Sub-station, Receiving Station 100.0% | Aggregate Area Of Recreational Open Space 100.0% | Open Parking 100.0% |
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | THE COSMOS CO OPERATIVE BANK LIMITED |
|---|---|
| IFSC | COSB0000099 |
| Branch Address | Ramchandra Road Kachpada Malad West Mumbai 400064 |