residential Project On Hold Source: rera.mh

OM GM Thakur City RERA Details - P99000024802, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for OM GM Thakur City under registration P99000024802 in Palghar, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000024802
  • Project Name GM THAKUR CITY
  • Project Type Others
  • Project Status Project On Hold
  • State MAHARASHTRA
  • District Palghar
  • Taluka Palghar
  • Village Man
  • Original Completion 30 January 2026
  • Project Area (in Sq.mt.) 7,094.42
  • Total Buildings/Towers 3
  • Documents 27 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 March 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 January 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S OM DEVELOPERS
Other Description NA

Promoters, Co-promoters & Members

NameRole
SHRI SURJIT KUMAR SURYRAJ SINGHAuthorized Signatory
SHRI SURJIT KUMAR SURYRAJ SINGHPartner
NARSINGH AVADH NARAYAN SINGHPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
GM THAKUR CITY RAGHURAJ VIHAR BLDG NO 2 WING A TYPE C1 WING B TYPE C2 2025-01-31 0 1 0 5 0 0 0
GM THAKUR CITY OM RESIDENCY BLDG NO 5 WING A TYPE C6 WING B TYPE C7 2023-01-31 0 1 0 5 0 0 0
GM THAKUR CITY OM RESIDENCY BLDG NO 6 WING A TYPE C8 WING B TYPE C9 2024-01-31 0 1 0 5 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 214
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 8 units · avg area 19.44 Sq.mt.
1 BHK 142 units · avg area 30.17 Sq.mt.
2 BHK 28 units · avg area 43.52 Sq.mt.
Shop 36 units · avg area 13.23 Sq.mt.
  • RAGHURAJ VIHAR BLDG NO 2 WING A TYPE C1 WING B TYPE C2
  • OM RESIDENCY BLDG NO 5 WING A TYPE C6 WING B TYPE C7
  • OM RESIDENCY BLDG NO 6 WING A TYPE C8 WING B TYPE C9
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 17.35 2 0
1RK 19.44 4 0
1BHK 28.22 12 0
1BHK 28.40 18 0
1BHK 30.48 20 0
1BHK 30.88 10 0
2BHK 43.76 8 0
Shop 7.48 2 0
Shop 10.66 2 0
Shop 13.06 2 0
Shop 14.21 2 0
Shop 15.70 2 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 60% Water Conservation Rainwater Harvesting 50% Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation 50% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply 50% Sewerage 50%
Storm Water Drains 60% Landscaping Tree Planting 60% Street Lighting 100%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • RAGHURAJ VIHAR BLDG NO 2 WING A TYPE C1 WING B TYPE C2
  • OM RESIDENCY BLDG NO 5 WING A TYPE C6 WING B TYPE C7
  • OM RESIDENCY BLDG NO 6 WING A TYPE C8 WING B TYPE C9
RAGHURAJ VIHAR BLDG NO 2 WING A TYPE C1 WING B TYPE C2 · Overall Progress 32%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
2 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
2 Building Plan Approval / NA Order For Plotted Development
3 Building Plan Approval / NA Order For Plotted Development
4 Building Plan Approval / NA Order For Plotted Development
5 Building Plan Approval / NA Order For Plotted Development
6 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
2 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
2 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021-22)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BASSEIN CATHOLIC CO OPERATIVE BANK
IFSC BACB0000043
Country/City