The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000010164
  • Project Name SHANTI VISTA
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Palghar
  • Taluka Palghar
  • Village khairepada
  • Original Completion 31 July 2018
  • Revised Completion 31 July 2018
  • Project Area (in Sq.mt.) 6,773.44
  • Total Buildings/Towers 1
  • Documents 10 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 24 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 July 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 July 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHAH REALTY AND INFRA

Promoters, Co-promoters & Members

NameRoleAddress
ASHIT RAMESH SHAHPartnerMumbai Suburban, MAHARASHTRA
CHANDRASHEKHAR SOORU POOJARIPartnerMumbai Suburban, MAHARASHTRA
ABHISHEK CHANDRASHEKHAR POOJARIPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHANTI VISTA SHANTI VISTA 0 22 6 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 249
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 86 units · avg area 38.75 Sq.mt.
1RK 36 units · avg area 25.72 Sq.mt.
2 BHK 91 units · avg area 50.41 Sq.mt.
3 BHK 8 units · avg area 68.17 Sq.mt.
SHOP 28 units · avg area 16.98 Sq.mt.
  • SHANTI VISTA
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
SHOP 17.14 2 2
1BHK 33.68 8 7
SHOP 17.0 4 4
1BHK 34.34 4 2
1BHK 33.46 2 2
1BHK 37.95 32 30
1BHK 41.12 40 26
2BHK 45.85 6 5
1RK 22.05 4 4
1RK 26.18 32 26
SHOP 12.64 1 0
SHOP 12.63 3 3
SHOP 15.05 4 4
3BHK 68.17 8 8
2BHK 52.71 24 24
SHOP 18.09 6 5
2BHK 50.3 56 56
2BHK 46.03 5 5
SHOP 12.52 4 2
SHOP 25.94 4 3
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SHANTI VISTA
SHANTI VISTA · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Approved Plan 16.Pdf.Pdf
2 Approved Plan 17.Pdf.Pdf
3 Approved Plan 14.Pdf.Pdf
4 Pan Card.Pdf.Pdf
5 Occupation Certificate.Pdf.Pdf
6 Title Report.Pdf.Pdf
7 Form B Affidavit Cum Declaration.Pdf.Pdf
8 Agreement Of Sale Letter.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0000573
Branch Address E 41 POONAM CHAMBERS SHANTI PARK MIRA ROAD EAST DIST THANE 401107