residential Ready to Move Source: rera.mh

Jivdani Vaibhav Laxmi RERA Details - P99000029993, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Jivdani Vaibhav Laxmi under registration P99000029993 in Palghar, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000029993
  • Project Name JIVDANI VAIBHAVLAXMI
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 31 December 2023
  • Project Area (in Sq.mt.) 2,369.45
  • Total Buildings/Towers 3
  • Documents 23 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 20 July 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
JIVDANI VAIBHAVLAXMI JIVDANI VAIBHAVLAXMI BUILDING NO 1 2023-12-31 0 24 0 5 6 15 6
JIVDANI VAIBHAVLAXMI JIVDANI VAIBHAVLAXMI BUILDING NO 2 2023-12-31 0 21 0 5 3 15 0
JIVDANI VAIBHAVLAXMI JIVDANI VAIBHAVLAXMI BUILDING NO 3 2023-12-31 0 27 0 5 6 15 6

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 65
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 36 units · avg area 23.22 Sq.mt.
1 BHK 29 units · avg area 33.40 Sq.mt.
  • JIVDANI VAIBHAVLAXMI BUILDING NO 1
  • JIVDANI VAIBHAVLAXMI BUILDING NO 2
  • JIVDANI VAIBHAVLAXMI BUILDING NO 3
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 18.40 1 0
1RK 19.79 1 0
1RK 23.32 4 0
1RK 24.25 8 0
1BHK 28.34 1 0
1BHK 31.13 4 0
1BHK 36.43 4 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 60% Water Conservation Rainwater Harvesting % not reported Energy Management 60%
Fire Protection And Fire Safety Requirements 60% Electrical Meter Room Substation Receivingstation 70% Aggregate Area Of Recreational Open Space % not reported
Open Parking 70% Water Supply 75% Sewerage 85%
Storm Water Drains % not reported Landscaping Tree Planting 70% Street Lighting 90%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal 85%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • JIVDANI VAIBHAVLAXMI BUILDING NO 1
  • JIVDANI VAIBHAVLAXMI BUILDING NO 2
  • JIVDANI VAIBHAVLAXMI BUILDING NO 3
JIVDANI VAIBHAVLAXMI BUILDING NO 1 · Overall Progress 74%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work70%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work90%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work80%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
2 Copy Of Layout Approval (In Case Of Layout)
3 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
2 Building Plan Approval / NA Order For Plotted Development
3 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
1 Other
2 Other
3 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank DOMBIVLI NAGARI SAHAKARI BANK LTD
IFSC DNSB0000042
Country/City