Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Partially Ready To Move Source: rera.mh

Topaz Heights RERA Details - P99000011693, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Topaz Heights under registration P99000011693 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000011693
  • Project Name TOPAZ HEIGHTS
  • Project Type Others
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 30 June 2021
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 461.37
  • Total Buildings/Towers 1
  • Documents 23 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2021 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name TOPAZ HOMES

Promoters, Co-promoters & Members

NameRoleAddress
JAGDISH NAIKPartnerPalghar, MAHARASHTRA
VINAYAK NAIKPartnerPalghar, MAHARASHTRA
NARESH VAZEPartnerPalghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
TOPAZ HEIGHTS TOPAZ HEIGHTS WING A AND WING B 0 1 13 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 125
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 104 units · avg area 1254.71 Sq.mt.
1RKPROPOSEDTOTAL 5 units · avg area 255.24 Sq.mt.
1RK APPROVD TOTAL 9 units · avg area 186.87 Sq.mt.
SHOP APPROVED TOTAL 7 units · avg area 84.36 Sq.mt.
  • TOPAZ HEIGHTS WING A AND WING B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK APPROVED TOTAL 1429.07 61 36
1RKPROPOSEDTOTAL 255.24 5 0
1BHK PROPOSED TOTAL 1007.37 43 0
1RK APPROVD TOTAL 186.87 9 7
SHOP APPROVED TOTAL 84.36 7 7
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 50.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • TOPAZ HEIGHTS WING A AND WING B
TOPAZ HEIGHTS WING A AND WING B · Overall Progress 51%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 LAYOUT.Pdf.Pdf
2 IOD.Pdf.Pdf
3 Plan Layout1.Pdf.Pdf
4 Plan Layout2.Pdf.Pdf
5 Plan Layout3.Pdf.Pdf
6 Plan Layout4.Pdf.Pdf
7 Plan Layout5.Pdf.Pdf
8 CC TOPAZ HOMES.Pdf.Pdf
9 PAN CARD TOPAZ.Pdf.Pdf
10 PAN CARD.Pdf.Pdf
11 Topaz Heights.Pdf.Pdf
12 POWER OF ATORMY.Pdf.Pdf
13 Topaz Format C Cir 28.Pdf.Pdf
14 SEARCH TITLE REPORT.Pdf.Pdf
15 FORM B DECLARATION AND ENCUMBRANCES.Pdf.Pdf
16 LEGAL TITLE FORMAT A.Pdf.Pdf
17 Form B.Pdf.Pdf
18 DEVIATION OF ALLOTMENT.Pdf.Pdf
19 2 Proforma Of Allotment Letter.Pdf.Pdf
20 DEVIATION OF AGREEMENT.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
IFSC BACB0000009
Branch Address NALLASOPARA WEST
Country/City