RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number UPRERAPRJ730714
- Project Name Coronation Amy Villa
- Project Type Mixed
- Project Status Under Construction
- State Uttar Pradesh
- District Lucknow
- Taluka Lucknow
- Authority Lucknow Development Authority
- Original Completion 12 February 2026
- Revised Completion 14 February 2025
- Project Area (in Sq.mt.) 3,666
- Documents 72 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Primary Promoter
CORONATION HOUSING AND DILIGENCE Partnership FirmLand, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Land Type Khasra | Plot No. 18 |
| Land Area (in Sq.mt.) 3,666 |
RERA Coordinates |
|
| Latitude, Longitude 26.85178, 80.93905 | |
Plans & Approvals
Statutory approvals obtained or pending against the project site.
| Permit Number | ResiComm Building/03161/LDA/BP/21-22/1248/04102021 |
|---|---|
| Permit Date | 01 January 2022 |
| Valid Upto | 31 December 2026 |
| Extendable Upto | 31 December 2029 |
Approval Documents
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Parks 100% | Demarcation Of Plots % not reported | Boundary Wall 100% |
| Road Work 100% | Footpaths % not reported | Water Supply Including Drinking Water Facilities % not reported |
| Sewer System % not reported | Drain 100% | Tree Planting 100% |
| Design For Electric Supply Including Street Lighting % not reported | Community Buildings % not reported | Treatment And Disposal System Of Sewage And Sullage Water % not reported |
| Solid Waste Management And Disposal System % not reported | Water Conservation System % not reported | Energy Management System Including Use Of Renewable Energy % not reported |
| Fire Protection And Fire Safety System % not reported | Social Infrastructure And Other Public Amenities Including Public Health Services % not reported | Emergency Evacuation Services % not reported |
| Other Miscellaneous Work % not reported |
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Cost (in Lacs) | ₹ 2,208 |
|---|---|
| Registration Fee | ₹ 35,250 |