residential Ready to Move Source: rera.mh

Phadke Residency RERA Details - P99000009007, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Phadke Residency under registration P99000009007 in Palghar, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000009007
  • Project Name VASTU SHILP DEVELOPERS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 31 January 2018
  • Revised Completion 31 January 2018
  • Project Area (in Sq.mt.) 1,540.0
  • Total Buildings/Towers 1
  • Documents 12 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 19 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 January 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 January 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name VASTU SHILP DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
ARUN VASUDEO NAIKPartnerPalghar, MAHARASHTRA
MINAL RAVINDRA PATILPartnerPalghar, MAHARASHTRA
NARENDRA CHINTAMAN KOREPartnerPalghar, MAHARASHTRA
VIVEK ACHYUT NAIKPartnerPalghar, MAHARASHTRA
VIPUL BALCHANDRA PATILPartnerPalghar, MAHARASHTRA
ANAND VASANT RAUTPartnerPalghar, MAHARASHTRA
RAVINDRA PURSHOTTAM PATILPartnerPalghar, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
VASTU SHILP DEVELOPERS PHADKE RESIDENCY 15 11 10 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 49
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 3 units · avg area 28.96 Sq.mt.
1 BHK 27 units · avg area 42.09 Sq.mt.
2 BHK 15 units · avg area 64.70 Sq.mt.
SHOP 4 units · avg area 22.60 Sq.mt.
  • PHADKE RESIDENCY
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
SHOP 26.67 1 0
SHOP 18.62 1 0
SHOP 26.16 1 0
SHOP 18.96 1 1
1RK 29.13 2 0
2BHK 64.7 15 13
1RK 28.62 1 1
1BHK 40.76 13 8
1BHK 43.32 14 8
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 80.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PHADKE RESIDENCY
PHADKE RESIDENCY · Overall Progress 90%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work88%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 LAYOUT VASTU.Pdf.Pdf
2 PLAN 2 VASTU.Pdf.Pdf
3 PLAN VASTU.Pdf.Pdf
4 Pancard Vastu.Pdf.Pdf
5 OC FINAL.Pdf.Pdf
6 FORM 4.Pdf.Pdf
7 Adct Tite Repot Vastu Compressed.Pdf.Pdf
8 TITILE INDEXII.Pdf.Pdf
9 Ibldr Delcaration.Pdf.Pdf
10 Regist Agrement Format.Pdf.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank VASAI VIKAS SAHAKARI BANK LIMITED
IFSC VVSB0000003
Branch Address THAKUR ARCADE NR RAILWAY STN VIRAR WEST 401303
Country/City