Rashmi Star City RERA Details - P99000005391, Palghar

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Rashmi Star City under registration P99000005391 in Palghar, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P99000005391
  • Project Name Rashmi Star City Phase 2
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Palghar
  • Taluka Vasai
  • Village Vasai-Virar City (M Corp)
  • Original Completion 30 June 2021
  • Revised Completion 30 December 2026
  • Project Area (in Sq.mt.) 8,885.96
  • Total Buildings/Towers 8
  • Documents 58 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 11 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2021 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Rashmi Realty Builders Pvt Ltd
Website www.rashmihousing.com
Other Description NA

Promoters, Co-promoters & Members

NameRole
Yogesh Pranjivan BosmiyaAuthorized Signatory
Ashok Pranjivan BosmiyaManaging Director

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
Rashmi Star City Phase 2 TYPE B9 2026-12-30 0 1 0 08 0 0 0
Rashmi Star City Phase 2 TYPE D1 2026-12-30 0 1 0 17 30 0 0
Rashmi Star City Phase 2 TYPE D2 2026-12-30 0 1 0 17 5 0 0
Rashmi Star City Phase 2 TYPE C12 2026-12-30 0 1 0 12 2 0 0
Rashmi Star City Phase 2 TYPE B12 2026-12-30 0 1 0 17 1 0 1
Rashmi Star City Phase 2 TYPE B13 2026-12-30 0 1 0 17 1 0 1
Rashmi Star City Phase 2 TYPE B11 2026-12-30 0 1 0 17 1 0 1
Rashmi Star City Phase 2 TYPE B10 2026-12-30 0 1 0 17 1 0 1
Rashmi Star City Phase 2 TYPE C13 2026-12-30 0 1 0 12 0 0 0
Rashmi Star City Phase 2 TYPE F1 2026-12-30 0 1 0 21 0 0 0
Rashmi Star City Phase 2 TYPE F2 2026-12-30 0 1 0 21 0 0 0
Rashmi Star City Phase 2 TYPE K1 2026-12-30 0 1 0 23 0 0 0
Rashmi Star City Phase 2 TYPE K2 2026-12-30 0 1 0 23 0 0 0
Rashmi Star City Phase 2 TYPE M1 2026-12-30 0 1 0 23 0 0 0
Rashmi Star City Phase 2 TYPE M2 2026-12-30 0 1 0 23 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 1915
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 58 units · avg area 21.54 Sq.mt.
1 BHK 1448 units · avg area 136.55 Sq.mt.
1 RK 68 units · avg area 20.99 Sq.mt.
2 BHK 232 units · avg area 309.63 Sq.mt.
COMMERCIAL 68 units · avg area 11.71 Sq.mt.
Shop 41 units · avg area 18.52 Sq.mt.
  • TYPE B9
  • TYPE D1
  • TYPE D2
  • TYPE C12
  • TYPE B12
  • TYPE B13
  • TYPE B11
  • TYPE B10
  • TYPE C13
  • TYPE F1
  • TYPE F2
  • TYPE K1
  • TYPE K2
  • TYPE M1
  • TYPE M2
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 22.94 16 16
1BHK 23.08 16 16
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 75% Water Conservation Rainwater Harvesting 10% Energy Management % not reported
Fire Protection And Fire Safety Requirements 90% Electrical Meter Room Substation Receivingstation 75% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage 50%
Storm Water Drains 75% Landscaping Tree Planting 50% Street Lighting 50%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 50% Solid Waste Management Disposal 50%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • TYPE B9
  • TYPE D1
  • TYPE D2
  • TYPE C12
  • TYPE B12
  • TYPE B13
  • TYPE B11
  • TYPE B10
TYPE B9 · Overall Progress 47%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
In Progress
% Work50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work40%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work25%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work25%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work25%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
2 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 A Details Of Encumbrances Concerned To Finance
1 B Details Of Encumbrances Concerned To Legal
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
2 Commencement Certificates / NA Order For Plotted Development
3 Commencement Certificates / NA Order For Plotted Development
4 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
2 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
7 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
8 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
9 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
10 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
11 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
8 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
9 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
10 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
11 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
12 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
13 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
14 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Certificates Of CA (Form 5)
1 Proforma Of Allotment Letter
1 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
2 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
3 Status Of Formation Of Legal Entity (Society/Co Op Etc.)
1 Other
2 Other
3 Other
4 Other
5 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Union Bank of India
IFSC UBIN0531928
Country/City