Ganraj Ghorpade Heights RERA Details - P51700029071, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ganraj Ghorpade Heights under registration P51700029071 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700029071
  • Project Name GHORPADE HEIGHTS
  • Project Type Residential / Group Housing
  • Project Status New Launch
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 March 2023
  • Revised Completion 30 March 2024
  • Project Area (in Sq.mt.) 330.0
  • Total Buildings/Towers 1
  • Documents 50 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 April 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GANRAJ DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
JASWANTKUMAR PARASMAL MODIPartnerThane, MAHARASHTRA
PRASAD BALARAM GHORPADEPartnerThane, MAHARASHTRA
PRADEEP PARASMAL MODIPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
GHORPADE HEIGHTS GHORPADE HEIGHTS 0 1 7 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 15
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 15 units · avg area 34.67 Sq.mt.
  • GHORPADE HEIGHTS
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 35.7 5 5
1BHK 32.9 5 5
1BHK 35.4 5 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • GHORPADE HEIGHTS
GHORPADE HEIGHTS · Overall Progress 82%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval NA Order For Plotted Development.Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration In FORM B.Pdf
8 2 Declaration In FORM B.Pdf
9 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
10 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
17 9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 10 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 11 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
21 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
22 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
23 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
24 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
25 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
26 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
27 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
28 9 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
29 10 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
30 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
31 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
32 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
33 2 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
34 1 Disclosure Of Sold Booked Inventory.Pdf
35 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
36 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
37 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
38 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
39 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
40 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
41 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
42 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
43 9 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
44 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
45 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
46 1 Proforma Of Allotment Letter.Pdf
47 1 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDIAN BANK
IFSC IDIB000B525
Branch Address BADLAPUR-WEST
Country/City