residential Ready to Move Source: rera.tg

Agalduty Raksha Residency RERA Details - P02200000320, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Agalduty Raksha Residency under registration P02200000320 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200000320
  • Project Name RAKSHA RESIDENCY
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 02 November 2023
  • Revised Completion 02 November 2023
  • Documents 22 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 16 February 2019 Expected commencement of civil works and foundation on site.
Original Completion 02 November 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 02 November 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name AGALDUTY RAJU
Other Description INDIVIDUALS

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
RAKSHA RESIDENCY RAKSHA RESIDENCY 2023-11-02 0 0 0 6 1 364

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 20
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 16 units · avg area 95.41 Sq.mt.
3 BHK 4 units · avg area 95.41 Sq.mt.
  • RAKSHA RESIDENCY
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 2BHK 95.41 False 4 0
1 2BHK 95.41 True 2 0
1 2BHK 95.41 False 2 0
2 2BHK 95.41 False 4 0
3 2BHK 95.41 False 4 0
4 3BHK 95.41 False 4 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 20 0 20
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 25% Water Supply 50% Sewerage 50%
Storm Water Drains % not reported Green Strip % not reported Street Lighting 20%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 10% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • RAKSHA RESIDENCY
RAKSHA RESIDENCY · Overall Progress 16%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work30%
X number of Slabs of Super Structure
In Progress
% Work25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work5%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/ Building Permit
Copy Of Sanctioned Building Plan
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B