RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P02200009515
- Project Name CNN DHANAMALL
- Project Type Commercial
- Project Status Under Construction
- Original Completion 17 December 2029
- Documents 408 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Slab | Total Parking Area |
|---|---|---|---|---|---|
| CNN DHANAMALL | CNN-DHANA MALL | 2029-12-17 | 3 | 8 | 31242 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- CNN-DHANA MALL
| Floor | Apartment Type | Carpet Area | Mortgage Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|---|---|
| GF | GROUND FLOOR | 7032.14 | False | 1 | 0 |
| 1 | FIRST FLOOR | 6989.78 | False | 1 | 0 |
| 2 | SECOND FLOOR | 7314.27 | True | 1 | 0 |
| 3 | THIRD FLOOR | 7417.36 | False | 1 | 0 |
| 4 | FOURTH FLOOR | 7105.74 | False | 1 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Covered Parking | 619 | 0 | 5 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Supply % not reported | Sewerage % not reported |
| Storm Water Drains % not reported | Green Strip % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room Substation Receivingstation % not reported | Aggregate Area Of Recreational Open Space % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- CNN-DHANA MALL
RERA Documents & Filings