RERA
RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P02400000743
- Project Name EMERALD
- Project Type Plotted Development
- Project Status Ready to Move
- Original Completion 06 January 2020
- Revised Completion 06 January 2020
- Documents 22 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
15 May 2019
Expected commencement of civil works and foundation on site.
Original Completion
06 January 2020
Mandated date for project handover to the allottees and final compliance filing.
Revised Completion
06 January 2020
No revision filed against the original committed handover date.
Promoter
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Father's Name
P VENKAT REDY
Location
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Supply 100% | Sewerage 100% |
| Storm Water Drains % not reported | Green Strip 100% | Street Lighting 100% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting 100% | Energy Management % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room Substation Receivingstation 100% | Aggregate Area Of Recreational Open Space 100% |
Documents
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.