RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P01100005209
- Project Name GARUDA RESIDENCY MYNA
- Project Type Residential
- Project Status Under Construction
- Original Completion 26 March 2027
- Documents 20 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| ANNANGI LOKESH | Authorized Signatory |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Slab | Total Parking Area |
|---|---|---|---|---|
| GARUDA RESIDENCY MYNA | GARUDA RESIDENCY MYNA | 2027-03-26 | 6 | 577 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- GARUDA RESIDENCY MYNA
| Floor | Apartment Type | Carpet Area | Mortgage Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|---|---|
| GF | 101 2bhk | 113.34 | True | 1 | 0 |
| GF | 102 2bhk | 111.5 | True | 1 | 0 |
| GF | 103 2bhk | 111.5 | True | 1 | 0 |
| GF | 104 2bhk | 111.5 | False | 1 | 0 |
| GF | 105 2bhk | 111.5 | False | 1 | 0 |
| GF | 106 2bhk | 111.5 | False | 1 | 0 |
| GF | 107 2bhk | 111.5 | False | 1 | 0 |
| GF | 108 2bhk | 111.5 | False | 1 | 0 |
| GF | 109 2bhk | 111.5 | False | 1 | 0 |
| GF | 110 2bhk | 113.34 | False | 1 | 0 |
| 1 | 201 2bhk | 113.34 | False | 1 | 0 |
| 1 | 202 2bhk | 111.5 | False | 1 | 0 |
| 1 | 203 2bhk | 111.5 | False | 1 | 0 |
| 1 | 204 2bhk | 111.5 | False | 1 | 0 |
| 1 | 205 2bhk | 111.5 | False | 1 | 0 |
| 1 | 206 2bhk | 111.5 | False | 1 | 0 |
| 1 | 207 2bhk | 111.5 | False | 1 | 0 |
| 1 | 208 2bhk | 111.5 | False | 1 | 0 |
| 1 | 209 2bhk | 111.5 | False | 1 | 0 |
| 1 | 210 2bhk | 113.34 | False | 1 | 0 |
| 2 | 301 2bhk | 113.34 | False | 1 | 0 |
| 2 | 302 2bhk | 111.5 | False | 1 | 0 |
| 2 | 303 2bhk | 111.5 | False | 1 | 0 |
| 2 | 304 2bhk | 111.5 | False | 1 | 0 |
| 2 | 305 2bhk | 111.5 | False | 1 | 0 |
| 2 | 306 2bhk | 111.5 | False | 1 | 0 |
| 2 | 307 2bhk | 111.5 | False | 1 | 0 |
| 2 | 308 2bhk | 111.5 | False | 1 | 0 |
| 2 | 309 2bhk | 111.5 | False | 1 | 0 |
| 2 | 310 2bhk | 113.34 | False | 1 | 0 |
| 3 | 401 2bhk | 113.34 | False | 1 | 0 |
| 3 | 402 2bhk | 111.5 | False | 1 | 0 |
| 3 | 403 2bhk | 111.5 | False | 1 | 0 |
| 3 | 404 2bhk | 111.5 | False | 1 | 0 |
| 3 | 405 2bhk | 111.5 | False | 1 | 0 |
| 3 | 406 2bhk | 111.5 | False | 1 | 0 |
| 3 | 407 2bhk | 111.5 | False | 1 | 0 |
| 3 | 408 2bhk | 111.5 | False | 1 | 0 |
| 3 | 409 2bhk | 111.5 | False | 1 | 0 |
| 3 | 410 2bhk | 113.34 | False | 1 | 0 |
| 4 | 501 2bhk | 113.34 | False | 1 | 0 |
| 4 | 502 2bhk | 111.5 | False | 1 | 0 |
| 4 | 503 2bhk | 111.5 | False | 1 | 0 |
| 4 | 504 2bhk | 111.5 | False | 1 | 0 |
| 4 | 505 2bhk | 111.5 | False | 1 | 0 |
| 4 | 506 2bhk | 111.5 | False | 1 | 0 |
| 4 | 507 2bhk | 111.5 | False | 1 | 0 |
| 4 | 508 2bhk | 111.5 | False | 1 | 0 |
| 4 | 509 2bhk | 111.5 | False | 1 | 0 |
| 4 | 510 2bhk | 113.34 | False | 1 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Covered Parking | 50 | 00 | 00 |
| Open Parking | 1075 | 00 | 00 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Supply 00% | Sewerage 00% |
| Storm Water Drains % not reported | Green Strip % not reported | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting 00% | Energy Management 00% | Fire Protection And Fire Safety Requirements 00% |
| Electrical Meter Room Substation Receivingstation 00% | Aggregate Area Of Recreational Open Space % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- GARUDA RESIDENCY MYNA
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.