RERA
RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P02400000584
- Project Name MODEL COUNTY
- Project Type Plotted Development
- Project Status Ready to Move
- Original Completion 15 March 2022
- Documents 27 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
10 April 2019
Expected commencement of civil works and foundation on site.
Original Completion
15 March 2022
Mandated date for project handover to the allottees and final compliance filing.
Promoter
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Organisation Type
Partnership
Individule Name
M/S GREEN CITY ESTATES
Promoters, Co-promoters & Members
Location
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 43% | Water Supply 43% | Sewerage 43% |
| Storm Water Drains % not reported | Green Strip 43% | Street Lighting 43% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting 43% | Energy Management % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room Substation Receivingstation 43% | Aggregate Area Of Recreational Open Space % not reported |
Documents
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.