Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.tg

Modi Greenwood Heights RERA Details - P02200001314, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Modi Greenwood Heights under registration P02200001314 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200001314
  • Project Name Greenwood Heights
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 21 September 2025
  • Documents 20 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 19 October 2019 Expected commencement of civil works and foundation on site.
Original Completion 21 September 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type LLP
Individule Name MEHTA AND MODI REALTY KAWKOOR LLP
Website www.modiproperties.com

Promoters, Co-promoters & Members

NameRole
Modi Properties Pvt Ltd represented by its M D Soham Satish ModiAuthorized Signatory
Anand Suresh MehtaPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
Greenwood Heights Greenwood Heights 2025-09-21 2 1 0 8 0 6491

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 121
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 117 units · avg area 853.65 Sq.mt.
A 414 to 417 4 units · avg area 722.80 Sq.mt.
  • Greenwood Heights
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF B 113 3 BHK 113.34 False 1 1
GF A 114 to 117 3 BHK 722.80 False 4 1
GF B 106 to 112 3 BHK 1115.31 False 7 4
GF A 101 to 105 3 BHK 796.65 False 5 0
1 A 201 to 205 3 BHK 796.65 True 5 0
1 B 213 3 BHK 113.34 True 1 0
1 A 217 3 BHK 180.70 False 1 0
1 B 206 to 212 3 BHK 1115.31 True 7 5
1 A 214 to 216 3 BHK 542.10 True 3 1
2 B 313 3 BHK 113.34 False 1 1
2 B 306 to 312 3 BHK 1115.31 False 7 3
2 A 314 to 317 3 BHK 728.80 False 4 2
2 A 301 to 305 3BHK 796.65 False 5 3
3 B 413 3 BHK 113.34 False 1 0
3 B 406 to 412 3BHK 1115.31 False 7 5
3 A 401 to 405 3BHK 796.65 False 5 2
3 A 414 to 417 722.80 False 4 3
4 A 114 to 117 3BHK 722.80 False 4 0
4 A 501 to 505 3BHK 796.65 False 5 3
4 B 506 to 512 3BHK 1115.31 False 7 3
4 B 513 3BHK 113.34 False 1 1
4 A 516 3BHK 132.01 True 1 1
4 A 515 3BHK 132.01 True 1 1
5 B 613 3 BHK 113.34 False 1 0
5 B 606 to 612 3BHK 1115.31 False 7 4
5 A 601 to 605 3 BHK 796.65 False 5 2
5 A 614 to 617 3 BHK 722.80 False 4 1
6 A 701 to 705 3BHK 796.65 False 5 0
6 B 713 3 BHK 113.34 False 1 0
6 A 714 to 717 3 BHK 722.80 False 4 0
6 B 706 to 712 3 BHK 1115.31 False 7 5
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 0 0 -
Open Parking 649145 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 25% Water Supply 100% Sewerage 100%
Storm Water Drains % not reported Green Strip 20% Street Lighting % not reported
Community Buildings 100% Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 20% Energy Management 100% Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space 20%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Greenwood Heights
Greenwood Heights · Overall Progress 70%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work83%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work45%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work70%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Form–1A Architects Certificate Overall Completion Of Registered Project
Local Authority Completion Certificate/Occupancy Certificate Doc/Final Layout Document
Country/City