RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P01100004828
- Project Name NAVYA THE EMPIRE - II
- Project Type Plotted Development
- Project Status Ready to Move
- Original Completion 05 February 2024
- Documents 28 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
01 August 2022
Expected commencement of civil works and foundation on site.
Original Completion
05 February 2024
Mandated date for project handover to the allottees and final compliance filing.
Promoter
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Organisation Type
Partnership
Individule Name
NAVYA DEVELOPERS
GST Number
36AAIFN5015G1ZF
Experience Details
Promoters, Co-promoters & Members
Location
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Supply % not reported | Sewerage % not reported |
| Storm Water Drains % not reported | Green Strip 99% | Street Lighting 98% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting 95% | Energy Management % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room Substation Receivingstation 69% | Aggregate Area Of Recreational Open Space % not reported |