Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.tg

NVR Sintra RERA Details - P02200003757, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for NVR Sintra under registration P02200003757 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200003757
  • Project Name SINTRA
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 23 August 2026
  • Documents 17 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 20 December 2021 Expected commencement of civil works and foundation on site.
Original Completion 23 August 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name N V R CONSTRUCTIONS
GST Number 36AAMFN9127D1Z4

Promoters, Co-promoters & Members

NameRole
NIMMA VENKAT RAM REDDYAuthorized Signatory
NIMMA SANDHYA RANIPartner
NIMMA AKHIL REDDYPartner
NIMMA AAKASH REDDYPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Slab No. of Slits Total Parking Area
SINTRA SINTRA 2026-08-15 6 1 374

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 15
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 5 units · avg area 115.19 Sq.mt.
3 BHK 10 units · avg area 141.44 Sq.mt.
  • SINTRA
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 3BHK 143.53 False 1 1
GF 3BHK 139.35 False 1 1
GF 2BHK 115.19 False 1 1
1 3BHK 143.53 True 1 1
1 3BHK 139.35 True 1 1
1 2BHK 115.19 False 1 1
2 3BHK 143.53 False 1 1
2 3BHK 139.35 False 1 1
2 2BHK 115.19 False 1 1
3 3BHK 143.53 False 1 1
3 3BHK 139.35 False 1 1
3 2BHK 115.19 False 1 1
4 3BHK 143.53 False 1 1
4 3BHK 139.35 False 1 1
4 2BHK 115.19 False 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 15 15 100
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply 100% Sewerage 100%
Storm Water Drains % not reported Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal 100%
Water Conservation Rainwater Harvesting 100% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SINTRA
SINTRA · Overall Progress 90%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Form–1A Architects Certificate Overall Completion Of Registered Project
Form–1A Architects Certificate Overall Completion Of Registered Project
Form–1A Architects Certificate Overall Completion Of Registered Project
Form–1A Architects Certificate Overall Completion Of Registered Project
Form–1A Architects Certificate Overall Completion Of Registered Project
Form–1A Architects Certificate Overall Completion Of Registered Project
Country/City