RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200001435
  • Project Name PRIDE EDA'S BRAHMA
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 30 October 2021
  • Documents 36 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 November 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 October 2021 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name PRIDE CONSTRUCTIONS
Experience Details
Project NameAddressLand AreaType of ProjectBuild Plot CountApartment countProject End Date
PRIDE ELITEKONDAPUR418.21Residential1127/05/2015
PRIDE SRINIVASA TOWERRAIDURG460.03Residential1119/07/2018

Promoters, Co-promoters & Members

NameRole
POTHIREDDY REDDEPPA REDDYPartner
PANNALA JANARDHAN REDDYPartner
RAVINDER REDDY NANCHERLAAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Slab Total Parking Area
PRIDE EDA'S BRAHMA PRIDE CASA BRAHMA 2021-10-30 7 2132

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 50
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 50 units · avg area 114.31 Sq.mt.
  • PRIDE CASA BRAHMA
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 2BHK 101 114.31 False 1 0
GF 2BHK 102 114.31 False 1 0
GF 2BHK 103 114.31 True 1 0
GF 2BHK 104 114.31 True 1 0
GF 2BHK 105 114.31 True 1 0
GF 2BHK 106 114.31 True 1 0
GF 2BHK 107 114.31 True 1 0
GF 2BHK 108 114.31 True 1 0
GF 2BHK 109 114.31 False 1 0
GF 2BHK 110 114.31 False 1 0
1 2BHK 201 114.31 False 1 0
1 2BHK 202 114.31 False 1 0
1 2BHK 203 114.31 False 1 0
1 2BHK 204 114.31 False 1 0
1 2BHK 205 114.31 False 1 0
1 2BHK 206 114.31 False 1 0
1 2BHK 207 114.31 False 1 0
1 2BHK 208 114.31 False 1 0
1 2BHK 209 114.31 False 1 0
1 2BHK 210 114.31 False 1 0
2 2BHK 301 114.31 False 1 0
2 2BHK 302 114.31 False 1 0
2 2BHK 303 114.31 False 1 0
2 2BHK 304 114.31 False 1 0
2 2BHK 305 114.31 False 1 0
2 2BHK 306 114.31 False 1 0
2 2BHK 307 114.31 False 1 0
2 2BHK 308 114.31 False 1 0
2 2BHK 309 114.31 False 1 0
2 2BHK 310 114.31 False 1 0
3 2BHK 401 114.31 False 1 0
3 2BHK 402 114.31 False 1 0
3 2BHK 403 114.31 False 1 0
3 2BHK 404 114.31 False 1 0
3 2BHK 405 114.31 False 1 0
3 2BHK 406 114.31 False 1 0
3 2BHK 407 114.31 False 1 0
3 2BHK 408 114.31 False 1 0
3 2BHK 409 114.31 False 1 0
3 2BHK 410 114.31 False 1 0
4 2BHK 501 114.31 False 1 0
4 2BHK 502 114.31 False 1 0
4 2BHK 503 114.31 False 1 0
4 2BHK 504 114.31 False 1 0
4 2BHK 505 114.31 False 1 0
4 2BHK 506 114.31 False 1 0
4 2BHK 507 114.31 False 1 0
4 2BHK 508 114.31 False 1 0
4 2BHK 509 114.31 False 1 0
4 2BHK 510 114.31 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 70 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply % not reported Sewerage % not reported
Storm Water Drains % not reported Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting % not reported Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PRIDE CASA BRAHMA
PRIDE CASA BRAHMA · Overall Progress 42%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Form–1A Architects Certificate Overall Completion Of Registered Project
Local Authority Completion Certificate/Occupancy Certificate Doc/Final Layout Document
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Proforma Of The Allotment Letter And Agreement For Sale