Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.tg

Sai Anandamai RERA Details - P02200006725, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sai Anandamai under registration P02200006725 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200006725
  • Project Name SAI ANANDAMAI BLOCK-A
  • Project Type Residential
  • Project Status Under Construction
  • Original Completion 22 June 2026
  • Documents 14 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 21 August 2023 Expected commencement of civil works and foundation on site.
Original Completion 22 June 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Proprietorship
Individule Name SAI INFRA
GST Number 36AJSPP2728B1Z3

Promoters, Co-promoters & Members

NameRole
PALLERLA SRINIVASA REDDYAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Slab Total Parking Area
SAI ANANDAMAI BLOCK-A SAI ANANDAMAI BLOCK-A 2026-06-22 6 183

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 10
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 10 units · avg area 115.40 Sq.mt.
  • SAI ANANDAMAI BLOCK-A
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 101 2BHK 115.4 True 1 0
GF 102 2BHK 115.4 True 1 0
1 201 2BHK 115.4 False 1 0
1 202 2BHK 115.4 False 1 0
2 301 2BHK 115.4 False 1 0
2 302 2BHK 115.4 False 1 0
3 401 2BHK 115.4 False 1 0
3 402 2BHK 115.4 False 1 0
4 501 2BHK 115.4 False 1 0
4 502 2BHK 115.4 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 10 00 00
Open Parking 183 00 00
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply 00% Sewerage 00%
Storm Water Drains 00% Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 00% Solid Waste Management Disposal 00%
Water Conservation Rainwater Harvesting 00% Energy Management 00% Fire Protection And Fire Safety Requirements 00%
Electrical Meter Room Substation Receivingstation 00% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SAI ANANDAMAI BLOCK-A
SAI ANANDAMAI BLOCK-A · Overall Progress 0%
Excavation
Not Started
% Work0%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Not Started
% Work0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Country/City