residential Under Construction Source: rera.tg

Sri Saranya Estancia RERA Details - P01100009018, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sri Saranya Estancia under registration P01100009018 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P01100009018
  • Project Name ESTANCIA
  • Project Type Residential
  • Project Status Under Construction
  • Original Completion 15 February 2026
  • Documents 26 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 June 2024 Expected commencement of civil works and foundation on site.
Original Completion 15 February 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name SRI SARANYA INFRA LLP
GST Number 36AEZFS3236H1ZG

Promoters, Co-promoters & Members

NameRole
ATLURI NITHINAuthorized Signatory
ATLURI VENKATA RATNAMManaging Director

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Slab Total Parking Area
ESTANCIA ESTANCIA 2026-02-15 1 1 643

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 25
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 15 units · avg area 122.78 Sq.mt.
3 BHK 10 units · avg area 182.55 Sq.mt.
  • ESTANCIA
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 3BHK 182.55 False 1 0
GF 3BHK 182.55 False 1 0
GF 2BHK 123.09 False 1 0
GF 2BHK 122.63 False 1 0
GF 2BHK 122.63 False 1 0
1 3BHK 182.55 True 1 0
1 3bhk 182.55 False 1 0
1 2bhk 123.09 True 1 0
1 2bhk 122.63 True 1 0
1 2bhk 122.63 False 1 0
2 3bhk 182.55 False 1 0
2 3bhk 182.55 False 1 0
2 2bhk 123.09 False 1 0
2 2bhk 122.63 False 1 0
2 2bhk 122.63 False 1 0
3 3bhk 182.55 False 1 0
3 3bhk 182.55 False 1 0
3 2bhk 123.09 False 1 0
3 2bhk 122.63 False 1 0
3 2bhk 122.63 False 1 0
4 3bhk 182.55 False 1 0
4 3bhk 182.55 False 1 0
4 2bhk 123.09 False 1 0
4 2bhk 122.63 False 1 0
4 2bhk 122.63 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 30 - 20
Open Parking 643 - 20
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 20% Water Supply 20% Sewerage 20%
Storm Water Drains 20% Green Strip 20% Street Lighting 20%
Community Buildings 20% Treatment And Disposal Of Sewage Sullage Water 20% Solid Waste Management Disposal 20%
Water Conservation Rainwater Harvesting 20% Energy Management 20% Fire Protection And Fire Safety Requirements 20%
Electrical Meter Room Substation Receivingstation 20% Aggregate Area Of Recreational Open Space 20%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • ESTANCIA
ESTANCIA · Overall Progress 16%
Excavation
In Progress
% Work20%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work20%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work20%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work20%
Excavation
In Progress
% Work20%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work20%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work20%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work20%
Excavation
In Progress
% Work20%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work20%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work20%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work20%
Excavation
In Progress
% Work20%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work20%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work20%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work20%
Excavation
In Progress
% Work20%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work20%
X number of Slabs of Super Structure
In Progress
% Work20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work20%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work20%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Details Of Encumbrances
Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Copy Of The Legal Title Report
Copy Of Approval Layout Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Country/City