Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.tg

SV Sai Urban Nest RERA Details - P02400004900, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for SV Sai Urban Nest under registration P02400004900 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02400004900
  • Project Name SAI URBAN NEST
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 07 January 2025
  • Documents 29 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 August 2022 Expected commencement of civil works and foundation on site.
Original Completion 07 January 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Father's Name V BAlAIAH
GST Number 36ADVPV3355R3Z7

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
SAI URBAN NEST VILLA 1 2025-01-07 0 0 0 3 0 70
SAI URBAN NEST VILLA 2 2025-01-07 0 0 0 3 0 68
SAI URBAN NEST VILLA 3 2025-01-07 0 0 0 3 0 66
SAI URBAN NEST VILLA 4 2025-01-07 0 0 0 3 0 64
SAI URBAN NEST VILLA 5 2025-01-07 0 0 0 3 0 61
SAI URBAN NEST VILLA 6 2025-01-07 0 0 0 3 1 59
SAI URBAN NEST VILLA 7 2025-01-07 0 0 0 3 0 65
SAI URBAN NEST VILLA 8 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 9 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 10 2025-01-07 0 0 0 3 0 57
SAI URBAN NEST VILLA 11 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 12 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 13 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 14 2025-01-07 0 0 0 3 0 55
SAI URBAN NEST VILLA 15 2025-01-07 0 0 0 3 0 46
SAI URBAN NEST VILLA 16 2025-01-07 0 0 0 3 0 46
SAI URBAN NEST VILLA 17 2025-01-07 0 0 0 3 0 46
SAI URBAN NEST VILLA 18 2025-01-07 0 0 0 3 0 46
SAI URBAN NEST VILLA 19 2025-01-07 0 0 0 3 0 68
SAI URBAN NEST VILLA 20 2025-01-07 0 0 0 3 0 68
SAI URBAN NEST VILLA 21 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 22 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 23 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 24 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 25 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 26 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 27 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 28 2025-01-07 0 0 0 3 0 56
SAI URBAN NEST VILLA 29 2025-01-07 0 0 0 3 0 49

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 29
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
4 BHK 29 units · avg area 302.48 Sq.mt.
  • VILLA 1
  • VILLA 2
  • VILLA 3
  • VILLA 4
  • VILLA 5
  • VILLA 6
  • VILLA 7
  • VILLA 8
  • VILLA 9
  • VILLA 10
  • VILLA 11
  • VILLA 12
  • VILLA 13
  • VILLA 14
  • VILLA 15
  • VILLA 16
  • VILLA 17
  • VILLA 18
  • VILLA 19
  • VILLA 20
  • VILLA 21
  • VILLA 22
  • VILLA 23
  • VILLA 24
  • VILLA 25
  • VILLA 26
  • VILLA 27
  • VILLA 28
  • VILLA 29
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 4 BHK 361.34 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 29 0 0
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Sewerage % not reported Internal Roads Footpaths % not reported Water Supply % not reported
Storm Water Drains % not reported Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 25% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VILLA 1
  • VILLA 2
  • VILLA 3
  • VILLA 4
  • VILLA 5
  • VILLA 6
  • VILLA 7
  • VILLA 8
  • VILLA 9
  • VILLA 10
  • VILLA 11
  • VILLA 12
  • VILLA 13
  • VILLA 14
  • VILLA 15
  • VILLA 16
  • VILLA 17
  • VILLA 18
  • VILLA 19
  • VILLA 20
  • VILLA 21
  • VILLA 22
  • VILLA 23
  • VILLA 24
  • VILLA 25
  • VILLA 26
  • VILLA 27
  • VILLA 28
  • VILLA 29
VILLA 1 · Overall Progress 55%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
In Progress
% Work85%
Stilt Floor
In Progress
% Work25%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work85%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work25%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work25%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Form–1A Architects Certificate Overall Completion Of Registered Project
Local Authority Completion Certificate/Occupancy Certificate Doc/Final Layout Document
Details Of Encumbrances
Country/City