Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.tg

The Royal Ridge RERA Details - P02200002708, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for The Royal Ridge under registration P02200002708 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200002708
  • Project Name THE ROYAL RIDGE
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 18 September 2025
  • Documents 17 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 March 2021 Expected commencement of civil works and foundation on site.
Original Completion 18 September 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name AVSM BUILDERS

Promoters, Co-promoters & Members

NameRole
GOURAVARAM SANTOSH KUMAR REDDYPartner
DURGEMPUDI SITARAM REDDYPartner
K VIJAY MOHAN REDDYPartner
SADU NARSIMHA REDDYPartner
PEDDABAVI SHYAM SUNDER REDDYPartner
MAMIDALA MADHUSUDHAN REDDYPartner
VOOTKURU JANAK REDDYPartner
GOURAVARAM ARAVIND REDDYAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Slab No. of Slits Total Parking Area
THE ROYAL RIDGE THE ROYAL RIDGE 2025-09-18 1 7 1 1985

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 25
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 25 units · avg area 184.76 Sq.mt.
  • THE ROYAL RIDGE
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 3BHK 178.44 False 1 0
GF 3BHK 178.83 False 1 0
GF 3BHK 185.80 False 1 1
GF 3BHK 185.80 False 1 1
GF 3BHK 185.80 False 1 1
1 3BHK 190.52 True 1 0
1 3BHK 178.44 True 1 0
1 3BHK 179.83 True 1 0
1 3BHK 185.80 False 1 1
1 3BHK 185.80 False 1 1
2 3BHK 178.44 False 1 0
2 3BHK 178.83 False 1 0
2 3BHK 191.91 False 1 0
2 3BHK 185.80 False 1 1
2 3BHK 185.80 False 1 1
3 3BHK 191.91 False 1 0
3 3BHK 185.80 False 1 1
3 3BHK 185.80 False 1 1
3 3BHK 185.80 False 1 1
3 3BHK 185.80 False 1 1
4 3BHK 178.83 False 1 0
4 3BHK 191.91 False 1 0
4 3BHK 185.80 False 1 1
4 3BHK 185.80 False 1 1
4 3BHK 185.80 False 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 51 0 0
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply 50% Sewerage 100%
Storm Water Drains % not reported Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 100% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 50% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • THE ROYAL RIDGE
THE ROYAL RIDGE · Overall Progress 80%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Status Of Conveyance
Status Of Conveyance
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Country/City