residential Under Construction Source: rera.tg

VR Sri Veena Residency RERA Details - P01100008705, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for VR Sri Veena Residency under registration P01100008705 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P01100008705
  • Project Name SRI VEENA RESIDENCY
  • Project Type Residential
  • Project Status Under Construction
  • Original Completion 15 July 2026
  • Documents 23 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 28 August 2024 Expected commencement of civil works and foundation on site.
Original Completion 15 July 2026 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name V R DEVELOPERS
GST Number 36AAQFV3477N1Z6

Promoters, Co-promoters & Members

NameRole
VENKATA DURGA PRASAD CHADALAVADAAuthorized Signatory
ASHA JYOTHI VEMULAPALLIPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
SRI VEENA RESIDENCY SRI VEENA RESIDENCY 2026-07-15 0 0 0 6 1 170

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 10
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 10 units · avg area 103.12 Sq.mt.
  • SRI VEENA RESIDENCY
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 101 2BHK 103.12 False 1 1
GF 102 2BHK 103.12 False 1 1
1 201 2BHK 103.12 True 1 0
1 202 2BHK 103.12 True 1 0
2 301 2BHK 103.12 False 1 0
2 302 2BHK 103.12 False 1 1
3 401 2BHK 103.12 False 1 1
3 402 2BHK 103.12 False 1 1
4 502 2BHK 103.12 False 1 0
4 501 2BHK 103.12 False 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 10 6 100
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply 100% Sewerage 100%
Storm Water Drains 100% Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 100% Solid Waste Management Disposal 100%
Water Conservation Rainwater Harvesting 100% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SRI VEENA RESIDENCY
SRI VEENA RESIDENCY · Overall Progress 80%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Form–1A Architects Certificate Overall Completion Of Registered Project
Local Authority Completion Certificate/Occupancy Certificate Doc/Final Layout Document
Copy Of The Legal Title Report
Copy Of The Legal Title Report
Proforma Of The Allotment Letter And Agreement For Sale
Country/City