residential Under Construction Source: rera.mh

Gurudev Orchid RERA Details - P51700052519, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Gurudev Orchid under registration P51700052519 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700052519
  • Project Name GURUDEV ORCHID
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Kalyan-Dombivali (M Corp.)
  • Original Completion 31 March 2025
  • Revised Completion 30 September 2026
  • Project Area (in Sq.mt.) 1,517.0
  • Total Buildings/Towers 1
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 September 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GURUDEV DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
MAHENDRAKUMAR DHANRAJ LUNIYAPartnerThane, MAHARASHTRA
YOGESH BALKRISHNA KHISMATRAOPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
GURUDEV ORCHID BUILDING D, PLOT A, PHASE I 0 0 7 7 7 53 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 53
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 35 units · avg area 39.58 Sq.mt.
2 BHK 14 units · avg area 59.75 Sq.mt.
Shop 4 units · avg area 27.80 Sq.mt.
  • BUILDING D, PLOT A, PHASE I
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 30.96 2 0
Shop 24.63 2 0
1BHK 37.91 7 1
2BHK 58.61 7 1
1BHK 39.21 14 0
1BHK 40.76 7 0
1BHK 40.79 7 0
2BHK 60.88 7 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 90.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt 90.0% Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING D, PLOT A, PHASE I
BUILDING D, PLOT A, PHASE I · Overall Progress 81%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work80%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work95%
Sanitary Fittings within the flats / premises
In Progress
% Work65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 B Details Of Encumbrances Concerned To Legal.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval NA Order For Plotted Development.Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
14 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
15 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
17 1 CERSAI Details.Pdf
18 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
19 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
20 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
21 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
22 1 Proforma Of Agreement For Sale.Pdf
23 1 Proforma Of Allotment Letter.Pdf
24 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
25 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
26 1 Deviation Report With Respect To Allotment Letter.Pdf
27 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
28 1 Other – Legal.Pdf
43 1 Disclosure Of Sold Booked Inventory.Pdf
45 1 Other – Technical.Pdf
51 Form 1.Pdf
52 Form 2.Pdf
53 Form 3.Pdf
54 Disclosure Of Sold And Booked Inventory.Pdf
91 Withdrawal Update Form 1.Pdf
92 Withdrawal Update Form 2.Pdf
93 Withdrawal Update Form 3.Pdf
94 Form 2A (FY 2023 2024).Pdf
95 Form 2A (FY 2024 2025).Pdf
96 Form 2A (FY 2025 2026).Pdf
97 Form 5 (FY 2024 2025).Pdf
98 Form 5 (FY 2025 2026).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UNION BANK OF INDIA
IFSC UBIN0532037
Branch Address MUSTAFA MANZIL, SHANKARRAO CHOWK, KALYAN, DIST THANE