HR Balaji Bizziland Complex RERA Details - P51700028044, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for HR Balaji Bizziland Complex under registration P51700028044 in Thane, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700028044
  • Project Name BALAJI BIZZILAND COMPLEX -PHASE I
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 30 September 2022
  • Project Area (in Sq.mt.) 1,421.42
  • Total Buildings/Towers 1
  • Documents 46 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 January 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2022 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name H R GADNIS AND ASSOCIATES
Other Description PROPRIETORSHIP

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
BALAJI BIZZILAND COMPLEX -PHASE I BUILDING F 2022-03-31 1 1 0 3 0 50 13

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 51
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 10 units · avg area 48.03 Sq.mt.
1RK 5 units · avg area 29.59 Sq.mt.
2 BHK 5 units · avg area 40.32 Sq.mt.
3 BHK 5 units · avg area 63.27 Sq.mt.
Shop 13 units · avg area 33.98 Sq.mt.
Office space 13 units · avg area 17.20 Sq.mt.
  • BUILDING F
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 34.54 1 0
Office space 11.11 2 0
Office space 12.10 1 0
Office space 13.27 1 0
Office space 13.41 1 0
Office space 13.99 2 0
Office space 14.46 1 0
Office space 14.57 1 0
Office space 15.78 1 0
1BHK 38.26 5 0
2BHK 40.32 5 0
1BHK 57.80 5 0
3BHK 63.27 5 0
Shop 37.09 1 0
Shop 41.44 1 0
Shop 20.14 1 0
Shop 21.76 1 0
Office space 21.12 1 0
Office space 27.24 1 0
Office space 41.48 1 0
1RK 29.59 5 0
Shop 35.10 1 0
Shop 45.81 1 1
Shop 49.11 2 2
Shop 22.64 1 0
Shop 23.98 1 0
Shop 28.74 1 0
Shop 32.24 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 13 0 50
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting % not reported Energy Management % not reported
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage % not reported
Storm Water Drains % not reported Landscaping Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING F
BUILDING F · Overall Progress 45%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work27%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work25%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 A Details Of Encumbrances Concerned To Finance
1 B Details Of Encumbrances Concerned To Legal
1 Copy Of Layout Approval (In Case Of Layout)
2 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval / NA Order For Plotted Development
2 Building Plan Approval / NA Order For Plotted Development
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
10 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
11 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1)
1 Engineer’S Certificate On Cost Incurred On Project (Form 2)
2 Engineer’S Certificate On Cost Incurred On Project (Form 2)
3 Engineer’S Certificate On Cost Incurred On Project (Form 2)
4 Engineer’S Certificate On Cost Incurred On Project (Form 2)
5 Engineer’S Certificate On Cost Incurred On Project (Form 2)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
1 CERSAI Details
2 CERSAI Details
3 CERSAI Details
1 Disclosure Of Interest In Other Real Estate Organizations
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021-22)
1 Proforma Of Agreement For Sale
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
1 Deviation Report With Respect To Allotment Letter
1 Deviation Report With Respect To Model Copy Of Agreement
1 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF INDIA
IFSC BKID0000505
Country/City