Lodha Codename Premier RERA Details - P51700077610, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Lodha Codename Premier under registration P51700077610 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700077610
  • Project Name Foresta E
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Mangaon
  • Original Completion 31 August 2028
  • Revised Completion 31 August 2028
  • Project Area (in Sq.mt.) 1,265.06
  • Total Buildings/Towers 1
  • Documents 46 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 October 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 August 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 August 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Lodha Developers Limited

Promoters, Co-promoters & Members

NameRoleAddress
Abhishek Mangalprabhat LodhaMDMumbai City, MAHARASHTRA
Mukund Manohar ChitaleDirectorMumbai City, MAHARASHTRA
Rajeev BakshiDirectorGurgaon, HARYANA
Harita GuptaDirectorSAj5mGOEcL7m2eluD1tCpuLgSaAcXcAAsvVkF7KFdnr3jcCMqh5YUyX0dkPQMozU, SAj5mGOEcL7m2eluD1tCpuLgSaAcXcAAsvVkF7KFdnr3jcCMqh5YUyX0dkPQMozU, Gurgaon, HARYANA
Rajinder Pal SinghDirectortuAk09GsJO1ZJUMm5bpZXGF8c3iYtGD5dNxVieF5U9tOZfngFyY7uc4wqKI6d9Dv, South West, NCT OF DELHI
Ashwani Ashwani KumarDirectorMumbai City, MAHARASHTRA
LEE ANTHONY POLISANO ANTHONY POLISANODirectorMumbai City, MAHARASHTRA
Shaishav DhariaDirectorMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Foresta E Foresta E 0 232 24 24 24 164 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 164
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 4 units · avg area 41.12 Sq.mt.
2 BHK 111 units · avg area 55.86 Sq.mt.
3 BHK 49 units · avg area 65.31 Sq.mt.
  • Foresta E
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK ULTIMA 55.86 107 0
2 BHK ULTIMA 56.13 2 0
3 BHK OPTIMA 65.23 46 0
3 BHK OPTIMA 64.92 2 0
3 BHK ULTIMA 69.82 1 0
1BHK 41.18 3 0
1BHK 40.95 1 0
2 BHK ULTIMA 55.49 2 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings 50.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Foresta E
Foresta E · Overall Progress 25%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work90%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work90%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Proforma Of Allotment Letter.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
9 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
10 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 1 Building Plan Approval NA Order For Plotted Development.Pdf
13 2 Building Plan Approval NA Order For Plotted Development.Pdf
14 3 Building Plan Approval NA Order For Plotted Development.Pdf
15 2 Other – Legal.Pdf
16 1 Other – Legal.Pdf
17 3 Other – Legal.Pdf
18 1 Declaration About Commencement Certificate.Pdf
19 1 CERSAI Details.Pdf
20 2 CERSAI Details.Pdf
21 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
22 1 Deviation Report With Respect To Allotment Letter.Pdf
23 1 B Details Of Encumbrances Concerned To Legal.Pdf
24 2 B Details Of Encumbrances Concerned To Legal.Pdf
25 1 Other – Finance.Pdf
26 1 Other – Technical.Pdf
27 2 Other – Technical.Pdf
28 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
29 1 Proforma Of Agreement For Sale.Pdf
30 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
31 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
32 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
132 1 Disclosure Of Sold Booked Inventory.Pdf
134 Form 1.Pdf
135 Form 2.Pdf
136 Form 3.Pdf
137 Disclosure Of Sold And Booked Inventory.Pdf
142 Self Declaration Of Quarterly Progress.Pdf
143 Others.Pdf
144 Withdrawal Update Form 1.Pdf
147 Withdrawal Update Form 2.Pdf
150 Withdrawal Update Form 3.Pdf
153 Form 2A (FY 2024 2025).Pdf
154 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank YES BANK
IFSC YESB0000001
Branch Address GROUND AND FIRST FLOOR,MOTI MAHAL, DR. ANNIE BESANT ROAD,, NEXT TO CITY BAKERY, WORLI, MUMBAI, MAHARASHTRA-400018
Country/City