residential Under Construction Source: rera.mh

Mohan Park Apartments RERA Details - P51700022013, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Mohan Park Apartments under registration P51700022013 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700022013
  • Project Name MOHAN PARK
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village mharal
  • Original Completion 30 March 2027
  • Revised Completion 30 March 2027
  • Project Area (in Sq.mt.) 7,850.0
  • Total Buildings/Towers 4
  • Documents 29 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 August 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 March 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MOHAN PARK BUILDING NO 2 4 12 9 7 7 28 NA
MOHAN PARK BUILDING NO 3 4 12 9 7 7 28 NA
MOHAN PARK BUILDING NO 4 4 12 9 7 7 28 NA
MOHAN PARK BUILDING NO 5 3 10 9 7 7 28 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 63.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting 25.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 45.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 35.0%
Electrical Meter Room, Sub-station, Receiving Station 60.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING NO 2
  • BUILDING NO 3
  • BUILDING NO 4
  • BUILDING NO 5
BUILDING NO 2 · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 Copy Of The Legal Title Report.Pdf
2 1 Details Of Encumbrances.Pdf
3 1 Copy Of Layout Approval (In Case Of Layout).Pdf
4 1 Building Plan Approval (IOD).Pdf
5 1 Commencement Certificates NA Order For Plotted Development.Pdf
6 1 Declaration In FORM B.Pdf
7 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
8 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
9 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
11 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
12 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
13 1 Disclosure Of Sold Booked Inventory.Pdf
14 1 Certificates Of CA (Form 3).Pdf
15 2 Certificates Of CA (Form 3).Pdf
16 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
17 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
18 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
19 1 Proforma Of Allotment Letter.Pdf
20 1 Other.Pdf
27 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
28 Form 1.Pdf
29 Form 2.Pdf
30 Form 3.Pdf
31 Disclosure Of Sold And Booked Inventory.Pdf
40 Form 5 (FY 2024 2025).Pdf
41 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UCO BANK
IFSC UCBA0000303
Branch Address Century Rayo, Murbad Rd Shahad,
Country/City