Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Sai Sakshi Aashiyana Shraddha And Saburi RERA Details - P51700026248, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sai Sakshi Aashiyana Shraddha And Saburi under registration P51700026248 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700026248
  • Project Name SAI AASHIYANA - II
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Tisgaon
  • Original Completion 30 June 2026
  • Revised Completion 30 June 2026
  • Project Area (in Sq.mt.) 1,670.0
  • Total Buildings/Towers 2
  • Documents 49 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 September 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Sai Sakshi Developers
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
SAI AASHIYANASURVEY NO 81-1 & 81-2 BEHIND JARI MARI MANDIR TISGAON Kalyan East 4213061860CompletedResidential / Group Housing21042016-06-302016-06-30NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Narender S KalaniPartnerThane, MAHARASHTRA
Chandrakant N BhosalePartnerThane, MAHARASHTRA
Rajesh C RaiPartnerThane, MAHARASHTRA
Vinay N KalaniPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SAI AASHIYANA - II BLDG-2 OR SIDDHI 0 15 10 0 0 NA
SAI AASHIYANA - II BLDG-1 OR RIDDHI 0 10 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 87
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 15 units · avg area 23.09 Sq.mt.
1 BHK 55 units · avg area 30.27 Sq.mt.
2 BHK 13 units · avg area 49.26 Sq.mt.
Shop 4 units · avg area 8.90 Sq.mt.
  • BLDG-2 OR SIDDHI
  • BLDG-1 OR RIDDHI
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 53.44 8 1
1RK 22.35 7 5
1BHK 27.48 8 6
1BHK 27.63 16 15
1BHK 37.72 8 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Cctv Surveilance 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BLDG-2 OR SIDDHI
  • BLDG-1 OR RIDDHI
BLDG-2 OR SIDDHI · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval NA Order For Plotted Development.Pdf
6 2 Building Plan Approval NA Order For Plotted Development.Pdf
7 3 Building Plan Approval NA Order For Plotted Development.Pdf
8 1 Commencement Certificates NA Order For Plotted Development.Pdf
9 2 Commencement Certificates NA Order For Plotted Development.Pdf
10 3 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
17 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
20 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
21 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
22 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
23 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
24 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
25 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
26 1 CERSAI Details.Pdf
27 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
28 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
29 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
30 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
33 1 Proforma Of Allotment Letter.Pdf
34 2 Proforma Of Allotment Letter.Pdf
35 3 Proforma Of Allotment Letter.Pdf
36 4 Proforma Of Allotment Letter.Pdf
37 5 Proforma Of Allotment Letter.Pdf
38 1 Proforma Of Agreement For Sale.Pdf
39 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
40 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
41 3 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
42 4 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
43 5 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
44 6 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
45 7 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
46 8 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
48 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0003145
Branch Address AXIS BANK , Kalyan East 421306
Country/City