Shubham Giriraj Swastik RERA Details - PM1330002500465, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shubham Giriraj Swastik under registration PM1330002500465 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PM1330002500465
  • Project Name GIRIRAJ SWASTIK 15-16 WING A
  • Project Type Mixed
  • Project Status New Launch
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 1,263.8
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 04 August 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S. SHUBHAM DEVELOPERS
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountProposed Completion DateLitigation PresentLitigation Details
JAI JHULELAL CO. OP. HSG. SOC.1025A, SERVICE ROAD, Kopri, thane (E), Thane (M Corp.), Thane, Thane, 400601, MAHARASHTRA1122.24OngoingResidential / Group Housing12024-12-31NoNA

Promoters, Co-promoters & Members

NameRoleAddress
RAJU KANAYALAL KHETWANIPartnerThane, MAHARASHTRA
MANOJ VELJI SHAHAuthorised SignatoryThane, MAHARASHTRA
BHAVNA BHARAT CHAVANPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
GIRIRAJ SWASTIK 15-16 WING A Giriraj Swastik 15-16 Wing A 6 35 15 Ground/Stilt+1st to 14th 15 96 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Giriraj Swastik 15-16 Wing A
Giriraj Swastik 15-16 Wing A · Overall Progress 63%
Excavation
In Progress
% Work85%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work90%
Stilt Floor
In Progress
% Work80%
Slabs of Super Structure
In Progress
% Work90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work40%
Sanitary Fittings within the flats / premises
In Progress
% Work40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work40%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Withdrawal Update Form 1.Pdf
5 Withdrawal Update Form 2.Pdf
9 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KARUR VYSYA BANK
IFSC KVBL0002108
Branch Address VIHAN VIHAR CO-OPERATIVE HOUSING SOCIETY LTD SHOP NO:123,OPP. GOWTHAM PARK SOCI
Country/City