residential Under Construction Source: rera.mh

SK Om Sai Imperial Towers RERA Details - PR1330002501669, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for SK Om Sai Imperial Towers under registration PR1330002501669 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PR1330002501669
  • Project Name OM SAI IMPERIAL TOWER 3
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Shahapur
  • Village Cherpoli
  • Original Completion 31 March 2030
  • Revised Completion 31 March 2030
  • Project Area (in Sq.mt.) 391.5
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 03 December 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2030 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2030 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountProposed Completion DateProject End DateLitigation PresentLitigation Details
Om Sai Imperial Tower110/136/B/14, Cherpoli, Shahapur, Cherpoli, Shahapur, Thane, 421601, MAHARASHTRA773.4CompletedResidential / Group Housing12026-12-312024-06-27NoNA
Om Sai Imperial Tower II137/1 , 137/2, 137/3, cherpoli, Shahapur, Cherpoli, Shahapur, Thane, 421601, MAHARASHTRA666OngoingResidential / Group Housing12028-03-31NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
OM SAI IMPERIAL TOWER 3 OM SAI IMPERIAL TOWER 3 23 7 Stilt + 6 6 18 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting 10.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 20.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • OM SAI IMPERIAL TOWER 3
OM SAI IMPERIAL TOWER 3 · Overall Progress 44%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Withdrawal Update Form 1.Pdf
3 Withdrawal Update Form 2.Pdf
5 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank FEDERAL BANK
IFSC FDRL0001878
Branch Address SHOP NOS 4 TO 7, S K SHRUSHTI COMPLEX OLD AGRA ROAD, NEAR GOVT REST HOUSE, THANE