Subhash Sumati Skyline RERA Details - P51700052640, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Subhash Sumati Skyline under registration P51700052640 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700052640
  • Project Name SUMATI SKYLINE
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Kalyan-Dombivali (M Corp.)
  • Original Completion 30 September 2026
  • Revised Completion 30 September 2026
  • Project Area (in Sq.mt.) 694.5
  • Total Buildings/Towers 1
  • Documents 39 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 September 2023 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SUBHASH SKYLINE INFRA

Promoters, Co-promoters & Members

NameRoleAddress
SUBHASH THANSING PATILPartnerThane, MAHARASHTRA
ADITYA VINAYAK AGTEPartnerThane, MAHARASHTRA
PALLAVI SUBHASH PATILPartnerThane, MAHARASHTRA
ARYAN SUBHASH PATILPartnerThane, MAHARASHTRA
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address X8zXMF6w1k70lHvKHpJJR9CEf0JpSD85VRlhJauYMb2343PIMyXIqI3ZOzhm9T/z

RERA Coordinates

Latitude, Longitude 19.2104591, 73.0846886

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SUMATI SKYLINE SUMATI SKYLINE 34 0 12 Ground + Stilt + First to Eleventh Floor 12 40 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 40
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 14 units · avg area 36.83 Sq.mt.
2 BHK 20 units · avg area 53.51 Sq.mt.
Shop 4 units · avg area 20.25 Sq.mt.
Office space 2 units · avg area 48.13 Sq.mt.
  • SUMATI SKYLINE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 37.35 9 7
2BHK 52.68 2 1
1BHK 35.77 4 3
2BHK 53.6 18 5
Shop 18.3 1 0
Shop 18.67 1 0
Shop 19.79 1 0
Shop 24.25 1 0
Office space 42.63 1 0
Office space 53.62 1 0
1BHK 36.42 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SUMATI SKYLINE
SUMATI SKYLINE · Overall Progress 82%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
Mh Details Html
Mh Certificate Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 B Details Of Encumbrances Concerned To Legal.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 1 Building Plan Approval NA Order For Plotted Development.Pdf
8 2 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
15 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
16 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
19 1 CERSAI Details.Pdf
20 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
21 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
22 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
23 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
24 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
25 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
26 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
27 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
28 1 Proforma Of Allotment Letter.Pdf
29 1 Proforma Of Agreement For Sale.Pdf
30 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
31 1 Deviation Report With Respect To Allotment Letter.Pdf
32 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
41 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
45 Withdrawal Update Form 1.Pdf
51 Withdrawal Update Form 2.Pdf
57 Withdrawal Update Form 3.Pdf
63 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000669
Branch Address COMMERCE CENTRE, TANDON ROAD, OPP PARKAR SADAN,DOMBIVLI EAST
Country/City