Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.tg

Concrete Crescent RERA Details - P02400001389, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Concrete Crescent under registration P02400001389 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02400001389
  • Project Name CONCRETE CRESCENT
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 06 July 2025
  • Documents 13 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 November 2019 Expected commencement of civil works and foundation on site.
Original Completion 06 July 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name CONCRETE INFRA AND DEVELOPERS

Promoters, Co-promoters & Members

NameRole
ANIL KUMAR REDDY ARANIAuthorized Signatory
ANIL KUMAR REDDY ARANIPartner
NARASIMHA GUMMADIDALAPartner
PRAVEEN KUMAR REDDY TAMMIREDDYPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
CONCRETE CRESCENT CONCRET CRESCENT 2021-06-30 1 1 0 7 1 6432

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 99
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 73 units · avg area 118.28 Sq.mt.
3 BHK 26 units · avg area 165.64 Sq.mt.
  • CONCRET CRESCENT
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 2 BHK 117.52 True 6 0
GF 2 BHK 117.52 False 3 0
GF 2 BHK 119.38 True 6 0
GF 3 BHK 158.40 False 3 0
GF 3 BHK 169.55 True 2 0
1 2 BHK 117.52 False 9 0
1 2 BHK 119.38 False 6 0
1 3 BHK 158.40 False 3 0
1 3 BHK 169.55 False 2 0
2 2 BHK 117.52 False 9 0
2 2 BHK 119.38 False 6 0
2 3 BHK 158.40 False 3 0
2 3 BHK 169.55 False 2 0
3 2 BHK 119.38 False 6 0
3 3 BHK 158.40 False 3 0
3 3 BHK 169.55 False 2 0
3 2 BHK 117.52 False 9 0
4 2 BHK 117.52 False 7 0
4 2 BHK 119.38 False 6 0
4 3 BHK 158.40 False 3 0
4 3 BHK 169.55 False 2 0
4 3BHK 235.04 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 219 0 100
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Supply 100% Sewerage 100%
Storm Water Drains 100% Green Strip 100% Street Lighting 100%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 100% Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 100% Energy Management 100% Fire Protection And Fire Safety Requirements 100%
Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • CONCRET CRESCENT
CONCRET CRESCENT · Overall Progress 100%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Complete
% Work100%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Country/City