RERA
RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P02400005169
- Project Name FORTUNE WEEKEND HOMES 27LP
- Project Type Plotted Development
- Project Status Ready to Move
- Original Completion 21 September 2023
- Documents 33 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
13 October 2022
Expected commencement of civil works and foundation on site.
Original Completion
21 September 2023
Mandated date for project handover to the allottees and final compliance filing.
Promoter
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Organisation Type
Company
Individule Name
FORTUNE INFRA DEVELOPERS PVT LTD
GST Number
36AAACF9926B1ZR
Website
www.fortunebutterflycity.com
Experience Details
Promoters, Co-promoters & Members
Location
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 60% | Water Supply 10% | Sewerage 65% |
| Storm Water Drains 50% | Green Strip 40% | Street Lighting 30% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
| Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room Substation Receivingstation % not reported | Aggregate Area Of Recreational Open Space % not reported |
Documents
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.