residential Ready to Move Source: rera.tg

GCR Ushodaya Residency RERA Details - P02200002939, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for GCR Ushodaya Residency under registration P02200002939 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02200002939
  • Project Name USHODAYA RESIDENCY
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 31 March 2023
  • Documents 12 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 14 May 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2023 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GCR BUILDERS
Experience Details
Project NameAddressLand AreaType of ProjectBuild Plot CountApartment countProject End Date
USHODAYA RESIDENCYROCK HILLS COLONY LB NAGAR HYDERABAD2508Residential16031/10/2014
USHODAYA RESIDENCYROCK HILLS COLONY LB NAGAR HYDERABAD2508Residential16031/10/2014
YASHODHA ENCLAVEYASHODHARA COLONY BAIRAMALGUDA LB NAGAR HYDERABAD1538.47Residential13531/05/2017
YASHODHA ENCLAVEYASHODHARA COLONY BAIRAMALGUDA LB NAGAR HYDERABAD1538.47Residential13531/05/2017
INDIRA PRIYADARSHINI APARTMENTINDIRA NAGAR COLONY SAHEB NAGAR KHURDU VANASTHALIPURAM RR DIST744Residential12017/12/2017
INDIRA PRIYADARSHINI APARTMENTINDIRA NAGAR COLONY SAHEB NAGAR KHURDU VANASTHALIPURAM RR DIST744Residential12017/12/2017
MADHURA RESIDENCYSAHEBNAGAR KHURDU VANASTHALIPURAM RR DIST1576.09Residential13531/12/2018
MADHURA RESIDENCYSAHEBNAGAR KHURDU VANASTHALIPURAM RR DIST1576.09Residential13531/12/2018

Promoters, Co-promoters & Members

NameRole
RAVINDER REDDY KADIREPartner
SUDHAKAR REDDY TUMKUNTAPartner
VENKATA SWAMY MANNEPALLIPartner
SHAIK SATHAR PASHAPartner
CHENNA REDDY GAVINIAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits Total Parking Area
USHODAYA RESIDENCY USHODAYA RESIDENCY 2023-03-31 0 0 0 6 1 319

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 15
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 5 units · avg area 105.91 Sq.mt.
3 BHK 10 units · avg area 145.63 Sq.mt.
  • USHODAYA RESIDENCY
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF 3BHK 144.46 False 1 0
GF 2BHK 105.91 False 1 0
GF 3BHK 146.79 False 1 0
1 3BHK 144.46 False 1 0
1 2BHK 105.91 True 1 0
1 3BHK 146.79 True 1 0
2 3BHK 144.46 False 1 0
2 2BHK 105.91 False 1 0
2 3BHK 146.79 False 1 0
3 3BHK 144.46 False 1 0
3 2BHK 105.91 False 1 0
3 3BHK 146.79 False 1 0
4 3BHK 144.46 False 1 0
4 2BHK 105.91 False 1 0
4 3BHK 146.79 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 16 0 32
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Supply 30% Sewerage % not reported
Storm Water Drains % not reported Green Strip % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting % not reported Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation % not reported Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • USHODAYA RESIDENCY
USHODAYA RESIDENCY · Overall Progress 31%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
In Progress
% Work90%
X number of Slabs of Super Structure
In Progress
% Work80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work40%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Land Title Search Report From An Advocate Having Experience Of At Least 10 Years
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Country/City