residential Ready to Move Source: rera.tg

Kakatiya Mango Leaf Ext RERA Details - P01100000663, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kakatiya Mango Leaf Ext under registration P01100000663 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P01100000663
  • Project Name MANGO LEAF EXT
  • Project Type Residential
  • Project Status Ready to Move
  • Original Completion 16 January 2025
  • Documents 57 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 April 2019 Expected commencement of civil works and foundation on site.
Original Completion 16 January 2025 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name KAKATIYA INFRA PROJECTS PRIVATE LIMITED(OPC)

Promoters, Co-promoters & Members

NameRole
KAKUMANU SRINIVASA RAOAuthorized Signatory
KAKUMANU SRINIVASA RAODirector

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Slab Total Parking Area
MANGO LEAF EXT VILLA NO 28 2019-05-22 3 0
MANGO LEAF EXT VILLA NO 29 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 30 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 31 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 32 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 33 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 34 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 35 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 36 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 37 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 38 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 39 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 40 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 41 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 42 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 43 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 44 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 45 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 46 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 47 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 48 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 49 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 50 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 51 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 52 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 53 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 54 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 55 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 56 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 57 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 58 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 59 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 60 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 61 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 62 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 63 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 64 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 65 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 66 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 67 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 68 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 69 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 70 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 71 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 72 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 73 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 74 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 75 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 76 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 77 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 78 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 79 2022-05-22 3 0
MANGO LEAF EXT VILLA NO 80 2022-05-22 3 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 53
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
3 BHK 53 units · avg area 192.52 Sq.mt.
  • VILLA NO 28
  • VILLA NO 29
  • VILLA NO 30
  • VILLA NO 31
  • VILLA NO 32
  • VILLA NO 33
  • VILLA NO 34
  • VILLA NO 35
  • VILLA NO 36
  • VILLA NO 37
  • VILLA NO 38
  • VILLA NO 39
  • VILLA NO 40
  • VILLA NO 41
  • VILLA NO 42
  • VILLA NO 43
  • VILLA NO 44
  • VILLA NO 45
  • VILLA NO 46
  • VILLA NO 47
  • VILLA NO 48
  • VILLA NO 49
  • VILLA NO 50
  • VILLA NO 51
  • VILLA NO 52
  • VILLA NO 53
  • VILLA NO 54
  • VILLA NO 55
  • VILLA NO 56
  • VILLA NO 57
  • VILLA NO 58
  • VILLA NO 59
  • VILLA NO 60
  • VILLA NO 61
  • VILLA NO 62
  • VILLA NO 63
  • VILLA NO 64
  • VILLA NO 65
  • VILLA NO 66
  • VILLA NO 67
  • VILLA NO 68
  • VILLA NO 69
  • VILLA NO 70
  • VILLA NO 71
  • VILLA NO 72
  • VILLA NO 73
  • VILLA NO 74
  • VILLA NO 75
  • VILLA NO 76
  • VILLA NO 77
  • VILLA NO 78
  • VILLA NO 79
  • VILLA NO 80
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF G PLUS TWO 3BHK 295.57 False 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 0 0 0
Open Parking 0 0 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 80% Water Supply 90% Sewerage 75%
Storm Water Drains 75% Green Strip 70% Street Lighting 50%
Community Buildings 70% Treatment And Disposal Of Sewage Sullage Water 60% Solid Waste Management Disposal % not reported
Water Conservation Rainwater Harvesting 90% Energy Management % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room Substation Receivingstation 75% Aggregate Area Of Recreational Open Space % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • VILLA NO 28
  • VILLA NO 29
  • VILLA NO 30
  • VILLA NO 31
  • VILLA NO 32
  • VILLA NO 33
  • VILLA NO 34
  • VILLA NO 35
  • VILLA NO 36
  • VILLA NO 37
  • VILLA NO 38
  • VILLA NO 39
  • VILLA NO 40
  • VILLA NO 41
  • VILLA NO 42
  • VILLA NO 43
  • VILLA NO 44
  • VILLA NO 45
  • VILLA NO 46
  • VILLA NO 47
  • VILLA NO 48
  • VILLA NO 49
  • VILLA NO 50
  • VILLA NO 51
  • VILLA NO 52
  • VILLA NO 53
  • VILLA NO 54
  • VILLA NO 55
  • VILLA NO 56
  • VILLA NO 57
  • VILLA NO 58
  • VILLA NO 59
  • VILLA NO 60
  • VILLA NO 61
  • VILLA NO 62
  • VILLA NO 63
  • VILLA NO 64
  • VILLA NO 65
  • VILLA NO 66
  • VILLA NO 67
  • VILLA NO 68
  • VILLA NO 69
  • VILLA NO 70
  • VILLA NO 71
  • VILLA NO 72
  • VILLA NO 73
  • VILLA NO 74
  • VILLA NO 75
  • VILLA NO 76
  • VILLA NO 77
  • VILLA NO 78
  • VILLA NO 79
  • VILLA NO 80
VILLA NO 28 · Overall Progress 48%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
In Progress
% Work80%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work70%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work60%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work70%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Details Of Encumbrances
Details Of Encumbrances
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/Copy Of Building Permit/Proceedings
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Copy Of The Legal Title Report
Commencement Certificate/Copy Of Building Permit/Proceedings
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Sanctioned Building Plan
Copy Of Board Resolution For Appointment Of Authorized Signatory In Case Of Other Than Individual
Country/City