RERA
RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P02400008961
- Project Name LOTUS GARDENS -VIII
- Project Type Plotted Development
- Project Status Ready to Move
- Original Completion 08 October 2029
- Documents 31 Verified
Timeline
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Proposed Start
08 October 2024
Expected commencement of civil works and foundation on site.
Original Completion
08 October 2029
Mandated date for project handover to the allottees and final compliance filing.
Promoter
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Organisation Type
Company
Individule Name
M/s.KIRTHANA PROPERTIES PRIVATE LIMITED
GST Number
36AADCK3046N1ZB
Promoters, Co-promoters & Members
Location
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
Development
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 95% | Water Supply 95% | Sewerage 80% |
| Storm Water Drains 75% | Green Strip 80% | Street Lighting 80% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water 90% | Solid Waste Management Disposal 90% |
| Water Conservation Rainwater Harvesting 85% | Energy Management % not reported | Fire Protection And Fire Safety Requirements 70% |
| Electrical Meter Room Substation Receivingstation 60% | Aggregate Area Of Recreational Open Space 70% |
Documents
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.