Western Dallas Center RERA Details - P02400000020, Hyderabad

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Western Dallas Center under registration P02400000020 in Hyderabad, Telangana. Data is sourced from rera.tg.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P02400000020
  • Project Name DALLAS CENTER
  • Project Type Commercial
  • Project Status Ready to Move
  • Original Completion 09 November 2023
  • Revised Completion 09 November 2023
  • Documents 15 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 29 November 2018 Expected commencement of civil works and foundation on site.
Original Completion 09 November 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 09 November 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S WESTERN CONSTRUCTIONS
Experience Details
Project NameAddressLand AreaType of ProjectBuild Plot CountApartment countProject End Date
WESTERN PEARLKONDAPUR6694.58Commercial11325/12/2014
WESTERN PEARLKONDAPUR6694.58Commercial11325/12/2014

Promoters, Co-promoters & Members

NameRole
SUDERSHAN REDDY RAuthorized Signatory
RAVI VARMA KANMURIPartner
SIVA RAMARAJU GPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Slab Total Parking Area
DALLAS CENTER DALLAS CENTER 2023-11-09 3 16 23610

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 16
Configurations 1
Inventory Type COMMERCIAL
Configuration Distribution
OFFICE SPACE 16 units · avg area 2321.70 Sq.mt.
  • DALLAS CENTER
Floor-Wise Inventory Explorer
Floor Apartment Type Carpet Area Mortgage Area No. of Apartment No. of Booked Apartment
GF OFFICE SPACE 2396.43 False 1 1
1 OFFICE SPACE 2583.35 False 1 1
2 OFFICE SPACE 2713.14 False 1 1
3 OFFICE SPACE 2713.14 False 1 1
4 OFFICE SPACE 2464.44 False 1 1
5 OFFICE SPACE 2464.44 False 1 1
6 OFFICE SPACE 2464.44 False 1 1
7 OFFICE SPACE 2464.44 False 1 1
8 OFFICE SPACE 2225.12 False 1 1
9 OFFICE SPACE 2225.12 False 1 1
10 OFFICE SPACE 2225.12 False 1 1
11 OFFICE SPACE 2225.12 False 1 1
12 OFFICE SPACE 1995.74 False 1 1
13 OFFICE SPACE 1995.74 False 1 1
14 OFFICE SPACE 1995.74 False 1 1
15 OFFICE SPACE 1995.74 False 1 1
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Covered Parking 686 0 20
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Supply 100% Sewerage 100%
Storm Water Drains 100% Green Strip 100% Street Lighting 100%
Community Buildings 100% Treatment And Disposal Of Sewage Sullage Water 100% Solid Waste Management Disposal 100%
Water Conservation Rainwater Harvesting 100% Energy Management 100% Fire Protection And Fire Safety Requirements 100%
Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space 100%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • DALLAS CENTER
DALLAS CENTER · Overall Progress 36%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
In Progress
% Work50%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
In Progress
% Work10%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Tg Details Html
Tg Certificate Pdf
Copy Of The Legal Title Report
Details Of Encumbrances
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Copy Of Approval Layout Plan
Proforma Of The Allotment Letter And Agreement For Sale
Declaration In FORM B
Commencement Certificate/ Building Permit
Commencement Certificate/ Building Permit
Copy Of Sanctioned Building Plan