Aarti Park RERA Details - P51700080241, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Aarti Park under registration P51700080241 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700080241
  • Project Name AARTI PARK
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Khadavali
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 1,295.0
  • Total Buildings/Towers 1
  • Documents 41 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 13 May 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name AARTI BUILDERS

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
AARTI PARK A WING AND B WING 108 11 9 9 9 84 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 84
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 48 units · avg area 28.96 Sq.mt.
Office space 21 units · avg area 15.32 Sq.mt.
Shop 15 units · avg area 16.10 Sq.mt.
  • A WING AND B WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 29.08 24 0
1BHK 29.63 6 0
Office space 16.31 1 0
Office space 22.74 1 0
Office space 26.23 1 0
Office space 64.36 1 0
Shop 22.52 1 0
Shop 25.1 1 0
Shop 28.75 1 0
Office space 7.75 1 0
Office space 9.25 1 0
Office space 9.26 5 0
Office space 12.44 3 0
Office space 12.46 2 0
Office space 16.08 1 0
Office space 16.1 1 0
Shop 8.47 1 0
Shop 9.01 1 0
Shop 11.97 1 0
Office space 9.94 1 0
Office space 12.22 2 0
Shop 12.67 3 0
Shop 13.33 1 0
Shop 16.8 4 0
Shop 17.11 1 0
1BHK 28.58 18 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A WING AND B WING
A WING AND B WING · Overall Progress 18%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

19 2 Other – Legal.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 Copy Of Layout Approval (In Case Of Layout).Pdf
7 1 Proforma Of Allotment Letter.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
10 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
11 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 2 Commencement Certificates NA Order For Plotted Development.Pdf
14 3 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Building Plan Approval NA Order For Plotted Development.Pdf
16 4 Other – Legal.Pdf
17 3 Other – Legal.Pdf
18 1 Other – Legal.Pdf
20 1 Declaration About Commencement Certificate.Pdf
21 1 CERSAI Details.Pdf
22 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
23 1 Deviation Report With Respect To Allotment Letter.Pdf
24 1 B Details Of Encumbrances Concerned To Legal.Pdf
25 2 B Details Of Encumbrances Concerned To Legal.Pdf
26 2 Other – Technical.Pdf
27 3 Other – Technical.Pdf
28 1 Other – Technical.Pdf
29 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
30 1 Proforma Of Agreement For Sale.Pdf
31 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
32 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
33 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
34 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
35 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
36 Form 1.Pdf
37 Form 2.Pdf
38 Form 3.Pdf
39 Disclosure Of Sold And Booked Inventory.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE KALYAN JANATA SAHAKARI BANK LTD.
IFSC KJSB0000012
Branch Address VASUNDHRA ARCADE,OPP.SHRI COMPLEX, BARAVE ROAD, KHADAKPADA,KALYAN(W)421301