RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P51700007222
- Project Name USHAJOSHI PARK PHASE II
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Thane
- Taluka Kalyan
- Village Khadavali
- Original Completion 31 December 2020
- Revised Completion 30 December 2021
- Project Area (in Sq.mt.) 6,700
- Total Buildings/Towers 4
- Documents 54 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| RAZI NISAR KUNGLE | Authorized Signatory |
| SALMAN ABUBAKAR THITTOO | Partner |
| VINAYAK ANANT JOSHI | Partner |
| ANANTAJI KRISHNA JOSHI | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| USHAJOSHI PARK PHASE II | B2 | 2020-12-31 | 0 | 1 | 0 | 4 | 0 | 1 | 0 |
| USHAJOSHI PARK PHASE II | F1 | 2020-12-31 | 0 | 1 | 0 | 4 | 0 | 1 | 0 |
| USHAJOSHI PARK PHASE II | C1 | 2020-12-31 | 0 | 1 | 0 | 4 | 0 | 1 | 0 |
| USHAJOSHI PARK PHASE II | BUILDING A, WING-B | 2020-12-31 | 0 | 1 | 0 | 4 | 0 | 1 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- B2
- F1
- C1
- BUILDING A, WING-B
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| S1 | 12.48 | 02 | 02 |
| S2 | 13.36 | 02 | 02 |
| S5 | 14.23 | 01 | 01 |
| S6 | 09.80 | 02 | 02 |
| S7 | 15.48 | 01 | 01 |
| S3 | 16.05 | 03 | 02 |
| S4 | 15.17 | 03 | 02 |
| S8 | 21.04 | 02 | 00 |
| R1 | 39.90 | 06 | 03 |
| R2 | 51.32 | 06 | 03 |
| R3 | 38.56 | 12 | 06 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1RK | 30.30 | 2 | 02 |
| 1BHK | 30.30 | 07 | 07 |
| 1BHK | 27.90 | 27 | 27 |
| 1BHK | 34.89 | 02 | 02 |
| 1BHK | 39.71 | 09 | 09 |
| 1BHK | 42.11 | 01 | 01 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| R1 | 38.56 | 12 | 07 |
| R2 | 39.90 | 10 | 06 |
| R3 | 40.87 | 02 | 01 |
| R4 | 45.48 | 02 | 01 |
| R5 | 51.32 | 06 | 04 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| S1 | 14.31 | 01 | 00 |
| S2 | 15.42 | 01 | 00 |
| S3 | 16.17 | 01 | 00 |
| S4 | 24.07 | 01 | 00 |
| R1 | 38.56 | 03 | 00 |
| R2 | 39.90 | 03 | 00 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation 80% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply 80% | Sewerage % not reported |
| Storm Water Drains % not reported | Landscaping Tree Planting 80% | Street Lighting 80% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- B2
- F1
- C1
- BUILDING A, WING-B
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | BANK OF BARODA |
|---|---|
| IFSC | BARB0TITWAL |