Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Adarsh Royal Villas RERA Details - P51700077636, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Adarsh Royal Villas under registration P51700077636 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700077636
  • Project Name ROYAL VILLAS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Bhiwandi
  • Village Bhiwandi (M Corp.)
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 747.04
  • Total Buildings/Towers 7
  • Documents 51 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 October 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name ADARSH ENTERPRISES

Promoters, Co-promoters & Members

NameRoleAddress
PRADEEP LAXMINARAYAN LAKHOTIAPartnerThane, MAHARASHTRA
IRFANAHMED SHAUKATALI KHANPartnerEjQReDl2pzEcGYBQMPhO0FjcAR8qMorFSPddmARXY9wYIDXkDcllLs79imYhgJG5, Thane, MAHARASHTRA
MUSTAFA TAIYEBALI NULWALAPartnerMumbai City, MAHARASHTRA
NILESH RAMESH KATHAWALEPartnerThane, MAHARASHTRA
VIMAL BHOORMAL JAINPartnerXmxXhMuiEeav44sQFV6s69q8kd9fM2nxnlouNJogvTtQpoY72Uf3GQpOL0Ajdpiw, Thane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
ROYAL VILLAS ADARSH PARK ROW HOUSE A1 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE B 02 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE B 04 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE B 06 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE C 03 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE C 05 1 0 2 2 2 1 NA
ROYAL VILLAS ADARSH PARK ROW HOUSE TYPE D 07 1 0 2 2 2 1 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 7
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
Bungalow 6 units · avg area 130.99 Sq.mt.
Shop 1 unit · avg area 131.04 Sq.mt.
  • ADARSH PARK ROW HOUSE A1
  • ADARSH PARK ROW HOUSE TYPE B 02
  • ADARSH PARK ROW HOUSE TYPE B 04
  • ADARSH PARK ROW HOUSE TYPE B 06
  • ADARSH PARK ROW HOUSE TYPE C 03
  • ADARSH PARK ROW HOUSE TYPE C 05
  • ADARSH PARK ROW HOUSE TYPE D 07
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Bungalow 130.43 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • ADARSH PARK ROW HOUSE A1
  • ADARSH PARK ROW HOUSE TYPE B 02
  • ADARSH PARK ROW HOUSE TYPE B 04
  • ADARSH PARK ROW HOUSE TYPE B 06
  • ADARSH PARK ROW HOUSE TYPE C 03
  • ADARSH PARK ROW HOUSE TYPE C 05
  • ADARSH PARK ROW HOUSE TYPE D 07
ADARSH PARK ROW HOUSE A1 · Overall Progress 83%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

9 1 Declaration In FORM B.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 3 A Details Of Encumbrances Concerned To Finance.Pdf
6 4 A Details Of Encumbrances Concerned To Finance.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Proforma Of Allotment Letter.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
12 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
13 1 Commencement Certificates NA Order For Plotted Development.Pdf
14 1 Building Plan Approval NA Order For Plotted Development.Pdf
15 2 Building Plan Approval NA Order For Plotted Development.Pdf
16 3 Building Plan Approval NA Order For Plotted Development.Pdf
17 4 Building Plan Approval NA Order For Plotted Development.Pdf
18 1 Declaration About Commencement Certificate.Pdf
19 1 CERSAI Details.Pdf
20 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
21 1 Deviation Report With Respect To Allotment Letter.Pdf
22 1 B Details Of Encumbrances Concerned To Legal.Pdf
23 2 B Details Of Encumbrances Concerned To Legal.Pdf
24 3 B Details Of Encumbrances Concerned To Legal.Pdf
25 4 B Details Of Encumbrances Concerned To Legal.Pdf
26 1 Other – Technical.Pdf
27 2 Other – Technical.Pdf
28 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
29 1 Proforma Of Agreement For Sale.Pdf
30 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
31 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
32 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
33 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
34 5 Disclosure Of Interest In Other Real Estate Organizations.Pdf
35 6 Disclosure Of Interest In Other Real Estate Organizations.Pdf
36 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
37 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
76 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
78 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
80 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
81 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
82 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
83 Form 1.Pdf
84 Form 2.Pdf
85 Form 3.Pdf
86 Disclosure Of Sold And Booked Inventory.Pdf
87 Withdrawal Update Form 1.Pdf
90 Withdrawal Update Form 2.Pdf
93 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0002056
Branch Address VARDHAMAN COMMERICAL COMPLEX,GF SHOP NO 7,8,9& 10.VILLAGE - KAMATGHAR,ANJUR PHATA BHIWANDI,THANE 421302