Aditya Thana CHS Sopan RERA Details - P51700002433, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Aditya Thana CHS Sopan under registration P51700002433 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700002433
  • Project Name Thana Co-Op Housing Society Sopan
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 December 2019
  • Revised Completion 30 December 2021
  • Project Area (in Sq.mt.) 3,290.05
  • Total Buildings/Towers 2
  • Documents 23 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2021 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Aditya Associates
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
BHARAT SADANBehind Telephone Exchange S V Road Naupada Thane West1066.9CompletedResidential / Group Housing1192015-08-062014-11-19NoNA
KAMATHE TOWERNear Shubamkaroti Hall Behind New English School Maharshi Karve Road Naupada Thane West1380CompletedResidential / Group Housing1192017-08-052016-09-27NoNA
GauriVishnu Nagar Naupada Thane West1133.75CompletedResidential / Group Housing1322017-08-312012-09-10NoNA
VrundavanHardas Wadi Village Chendani Thane East561.5CompletedResidential / Group Housing1122012-12-312013-11-18NoNA
YashodeepBehind HDFC Bank haras Wadi Kopri Colony Thane East603.4CompletedResidential / Group Housing1192013-06-022013-12-19NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Arvind Achyut DatarPartnerThane, MAHARASHTRA
Arun Achyut DatarPartnerThane, MAHARASHTRA
AMIT ARUN DATARPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Thana Co-Op Housing Society Sopan Buliding A 0 1 8 0 0 NA
Thana Co-Op Housing Society Sopan Building B 10 1 27 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 138
Configurations 24
Inventory Type RESIDENTIAL
Configuration Distribution
1 1 unit · avg area 1.00 Sq.mt.
Shop 1 1 unit · avg area 26.16 Sq.mt.
1 BHK 17 units · avg area 37.42 Sq.mt.
1 Room Kitchen 1 unit · avg area 22.74 Sq.mt.
1RK 1 unit · avg area 32.57 Sq.mt.
2 BHK 77 units · avg area 62.83 Sq.mt.
Shop2 1 unit · avg area 24.27 Sq.mt.
Shop 3 1 unit · avg area 25.81 Sq.mt.
Shop 4 1 unit · avg area 27.68 Sq.mt.
Shop5 1 unit · avg area 24.48 Sq.mt.
Multipurpose Room 1 unit · avg area 20.36 Sq.mt.
Shop 1 unit · avg area 14.84 Sq.mt.
MultipurposeRoom 23 units · avg area 17.48 Sq.mt.
ShopK 1 unit · avg area 55.14 Sq.mt.
ShopJ 1 unit · avg area 11.21 Sq.mt.
ShopI 1 unit · avg area 32.34 Sq.mt.
Shop A 1 unit · avg area 21.97 Sq.mt.
ShopC 1 unit · avg area 15.72 Sq.mt.
ShopD 1 unit · avg area 16.66 Sq.mt.
ShopH 1 unit · avg area 15.35 Sq.mt.
ShopE 1 unit · avg area 16.56 Sq.mt.
ShopF 1 unit · avg area 16.41 Sq.mt.
ShopL 1 unit · avg area 53.17 Sq.mt.
ShopG 1 unit · avg area 15.39 Sq.mt.
  • Buliding A
  • Building B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK 59.25 1 0
Shop5 24.48 1 1
Shop 4 27.68 1 1
Multipurpose Room 20.36 1 0
2 BHK C 57.5 4 0
2 BHK B 59.93 4 0
1 1.0 1 1
Shop 1 26.16 1 1
Shop2 24.27 1 0
Shop 3 25.81 1 0
1 BHK 36.1 2 0
2 BHK A 56.16 1 0
1 Room Kitchen 22.74 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Buliding A
  • Building B
Buliding A · Overall Progress 15%
Excavation
Complete
% Work100%
Basement (if any)
In Progress
% Work30%
Podiums (if any)
Not Started
% Work0%
Plinth
In Progress
% Work30%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration In FORM B.Pdf
8 2 Declaration In FORM B.Pdf
9 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
11 1 Certificates Of CA (Form 3).Pdf
12 1 Certificates Of CA (Form 5).Pdf
13 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
14 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
15 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
16 1 Proforma Of Allotment Letter.Pdf
17 2 Proforma Of Allotment Letter.Pdf
18 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
19 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
20 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank TJSB SAHAKARI BANK LTD
IFSC TJSB0000002
Branch Address Madhumalti, Veer Savarkar Path, Thane West