residential Under Construction Source: rera.mh

Deep Laxmi Shreeji Z Plus RERA Details - P51700079117, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Deep Laxmi Shreeji Z Plus under registration P51700079117 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700079117
  • Project Name SHREEJI Z PLUS
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 30 June 2029
  • Revised Completion 30 June 2029
  • Project Area (in Sq.mt.) 2,168.06
  • Total Buildings/Towers 1
  • Documents 44 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 06 February 2025 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2029 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2029 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name DEEP LAXMI ASSOCIATES

Promoters, Co-promoters & Members

NameRoleAddress
SATEJ HITENDRA PATELPartnerRaigarh, MAHARASHTRA
KANTILAL MAVJI PATELPartnerRaigarh, MAHARASHTRA
MOHANLAL HANSRAJ PATELPartnerRaigarh, MAHARASHTRA
MANOHAR KANU MHASKARPartnerThane, MAHARASHTRA
VIKAS RAGHUNATH GUPTEPartnerThane, MAHARASHTRA
PRANALI SHAILESH MHASKARPartnerThane, MAHARASHTRA
CHANDRASHEKHAR MANOHAR MHASKARPartnerThane, MAHARASHTRA
JAYASHRI VIKAS GUPTEPartnerMumbai City, MAHARASHTRA
KETKI ANIKET TAMHANEPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHREEJI Z PLUS BLDG A 0 92 19 19 19 109 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 109
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 2 units · avg area 54.28 Sq.mt.
3 BHK 80 units · avg area 68.51 Sq.mt.
4 BHK 14 units · avg area 79.07 Sq.mt.
Shop 13 units · avg area 23.30 Sq.mt.
  • BLDG A
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 27.87 1 0
2BHK 53.25 1 0
Shop 17.89 1 0
Shop 18.92 1 0
Shop 21.19 1 0
Shop 21.29 1 0
Shop 21.61 1 0
Shop 22.45 1 0
Shop 22.57 1 0
Shop 23.0 1 0
Shop 24.28 1 0
2BHK 55.31 1 0
Shop 24.66 1 0
Shop 27.91 1 0
Shop 29.28 1 0
3BHK 67.69 32 0
3BHK 66.74 2 0
3BHK 66.48 13 0
4BHK 79.07 14 0
3BHK 71.85 16 0
3BHK 69.49 2 0
3BHK 68.81 2 0
3BHK 68.54 13 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BLDG A
BLDG A · Overall Progress 0%
Stilt Floor
Not Started
% Work0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Proforma Of Allotment Letter.Pdf
7 1 Declaration In FORM B.Pdf
8 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
9 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
10 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 2 Commencement Certificates NA Order For Plotted Development.Pdf
13 3 Commencement Certificates NA Order For Plotted Development.Pdf
14 4 Building Plan Approval NA Order For Plotted Development.Pdf
15 1 Building Plan Approval NA Order For Plotted Development.Pdf
16 2 Building Plan Approval NA Order For Plotted Development.Pdf
17 3 Building Plan Approval NA Order For Plotted Development.Pdf
18 1 Other – Legal.Pdf
19 2 Other – Legal.Pdf
20 1 Disclosure Of Sold Booked Inventory.Pdf
21 1 Declaration About Commencement Certificate.Pdf
22 2 Declaration About Commencement Certificate.Pdf
23 1 CERSAI Details.Pdf
24 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
25 1 Deviation Report With Respect To Allotment Letter.Pdf
26 1 B Details Of Encumbrances Concerned To Legal.Pdf
27 2 B Details Of Encumbrances Concerned To Legal.Pdf
28 1 Other – Technical.Pdf
29 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
30 1 Proforma Of Agreement For Sale.Pdf
31 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
32 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
33 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
37 Form 1.Pdf
38 Form 2.Pdf
39 Form 3.Pdf
40 Disclosure Of Sold And Booked Inventory.Pdf
41 Self Declaration Of Quarterly Progress.Pdf
42 Withdrawal Update Form 1.Pdf
45 Withdrawal Update Form 2.Pdf
48 Withdrawal Update Form 3.Pdf
51 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0001349
Branch Address SHOP NO.2,3,13 & 14, “SHREEJI DEVELOPERS”, KATRAP NAKA, BADLAPUR – 421503 DISTRICT – THANE
Country/City