Dinkar Plaza RERA Details - P51700004644, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Dinkar Plaza under registration P51700004644 in Thane, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700004644
  • Project Name DINKAR PLAZA
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Thane
  • Taluka Kalyan
  • Village KHADEGOLAVALI
  • Original Completion 31 December 2021
  • Revised Completion 30 December 2022
  • Project Area (in Sq.mt.) 2,284.69
  • Total Buildings/Towers 2
  • Documents 45 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2021 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2022 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name DREAM HOME INFRA
Other Description NA

Promoters, Co-promoters & Members

NameRole
RAJENDRA MRITUNJAY SINGHPartner
GIRISH VASANT PAWSHEPartner
ASHUTOSH SABHANARAYAN MISHRAPartner
RAJENDRAPAL MRITUNJAY SINGHAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
DINKAR PLAZA DINKAR PLAZA B WING 2022-12-01 00 02 00 08 02 00 02
DINKAR PLAZA DINKAR PLAZA A WING 2022-12-30 00 01 00 08 01 00 01

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 59
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 21 units · avg area 43.14 Sq.mt.
2 BHK 34 units · avg area 950.34 Sq.mt.
3 BHK 1 unit · avg area 71.42 Sq.mt.
Shop 3 units · avg area 17.83 Sq.mt.
  • DINKAR PLAZA B WING
  • DINKAR PLAZA A WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 AND 2 BHK SHOPS 1142 28 00
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 000 000 00
Covered Parking 05 01 100
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting 100% Energy Management 100%
Fire Protection And Fire Safety Requirements 100% Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply 100% Sewerage 100%
Storm Water Drains 100% Landscaping Tree Planting 100% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • DINKAR PLAZA B WING
  • DINKAR PLAZA A WING
DINKAR PLAZA B WING · Overall Progress 0%
Excavation
Not Started
% Work0%
X number of Basement(s) and Plinth
Not Started
% Work0%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Not Started
% Work0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Not Started
% Work0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Not Started
% Work0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Not Started
% Work0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
2 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 A Details Of Encumbrances Concerned To Finance
3 A Details Of Encumbrances Concerned To Finance
1 B Details Of Encumbrances Concerned To Legal
2 B Details Of Encumbrances Concerned To Legal
1 Copy Of Layout Approval (In Case Of Layout)
2 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
2 Declaration About Commencement Certificate
1 Declaration In FORM B
2 Declaration In FORM B
3 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2022-23)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
3 Disclosure Of Sold/ Booked Inventory
4 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021-22)
1 Proforma Of Agreement For Sale
1 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank YES BANK
IFSC YESB0000125
Country/City