Gayatri Niwas RERA Details - P51700029816, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Gayatri Niwas under registration P51700029816 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700029816
  • Project Name GAYATRI NIWAS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Chikanghar
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 969.9
  • Total Buildings/Towers 1
  • Documents 37 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 July 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Gayatri Builders

Promoters, Co-promoters & Members

NameRoleAddress
Ashok Hotchand GangwaniPartnerThane, MAHARASHTRA
Vaibhav Dattaram DurvePartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
GAYATRI NIWAS GAYATRI NIWAS 0 47 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 44
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 11 units · avg area 38.28 Sq.mt.
2 BHK 19 units · avg area 54.82 Sq.mt.
3 BHK 14 units · avg area 74.68 Sq.mt.
  • GAYATRI NIWAS
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 46.41 4 4
1BHK 43.16 1 1
3BHK 70.98 3 3
1BHK 39.54 5 5
3BHK 66.09 2 2
2BHK 56.42 2 2
2BHK 58.87 2 2
2BHK 56.1 2 2
2BHK 54.83 1 1
2BHK 58.84 2 2
2BHK 55.09 4 4
3BHK 97.49 1 1
1BHK 39.07 1 1
3BHK 95.74 1 1
2BHK 57.28 1 1
3BHK 69.66 1 1
1BHK 35.88 2 2
3BHK 72.28 5 5
1BHK 34.67 2 2
2BHK 63.05 1 1
3BHK 76.12 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • GAYATRI NIWAS
GAYATRI NIWAS · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 Copy Of The Legal Title Report.Pdf
2 1 Details Of Encumbrances.Pdf
3 1 Copy Of Layout Approval (In Case Of Layout).Pdf
4 1 Building Plan Approval NA Order For Plotted Development.Pdf
5 2 Building Plan Approval NA Order For Plotted Development.Pdf
6 3 Building Plan Approval NA Order For Plotted Development.Pdf
7 4 Building Plan Approval NA Order For Plotted Development.Pdf
8 5 Building Plan Approval NA Order For Plotted Development.Pdf
9 6 Building Plan Approval NA Order For Plotted Development.Pdf
10 7 Building Plan Approval NA Order For Plotted Development.Pdf
11 1 Commencement Certificates NA Order For Plotted Development.Pdf
12 2 Commencement Certificates NA Order For Plotted Development.Pdf
13 3 Commencement Certificates NA Order For Plotted Development.Pdf
14 4 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Declaration About Commencement Certificate.Pdf
16 1 Declaration In FORM B.Pdf
17 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
18 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
19 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
20 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
21 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
22 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
23 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
24 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
25 1 Disclosure Of Sold Booked Inventory.Pdf
26 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
27 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
28 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
29 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
30 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
31 1 Proforma Of Allotment Letter.Pdf
32 2 Proforma Of Allotment Letter.Pdf
33 3 Proforma Of Allotment Letter.Pdf
34 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
35 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000456
Branch Address TILAK CHOWK, KALYAN WEST
Country/City